Construction methods · Caissons and marine foundations

Jack-up platforms

A barge with legs that are lowered to the seabed and then jack the hull above the waves, giving a steady drilling or piling deck in 5-40 m of water. Weather-independent once elevated, it is the platform behind most bored pile work at sea.

Also called: self-elevating platform, jack-up barge, SEP

Jack-up platforms — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Carry out a site-specific assessment (ISO 19905-1): leg penetration and punch-through risk from CPTs or borings at each location, seabed obstructions, scour, and metocean limits for moving and for the elevated condition.
  2. Tow or self-propel to location in a weather window and position with GNSS, anchors or tugs.
  3. Lower the legs to touchdown and pre-load each footing, by ballast water or leg by leg, to at least the largest reaction expected in the design storm, watching for sudden penetration. Hold point.
  4. Jack the hull to the working air gap above the design wave crest.
  5. Work from the deck (drilling, piling, cap formwork) within the deck-load and crane charts; re-check leg penetration and scour around the footings periodically.
  6. Jack down, extract the legs (jetting where they are deep in clay) and move to the next pier.

Key numbers

Where it fits

  • Bored piles, drilling investigation, pile caps and pier construction at sea and in estuaries; water 5-40 m.

Where it does not

  • Very soft seabeds with punch-through risk, rock outcrops, strong currents beyond the leg capacity.

Choosing it

Plant, pace and money

PlantJack-up 30-90 m with 100-300 t crane, legs to 60 m.
ProductivityMoves take a day; the deck then works around the clock.
CostUSD 20,000-80,000 per day; the game's jack-up rate.

Risks and controls

What goes wrong

  • Punch-through of a leg during preload (the major jack-up accident), leg damage, collision.

Quality assurance

Site-specific leg penetration assessment, preload records, weather limits enforced.

Origins

Self-elevating platforms were developed for offshore drilling in the Gulf of Mexico in the 1950s; construction jack-ups derived from them became the standard platform for marine piling and, later, offshore wind installation.

Examples

All Gulf sea bridges, Hong Kong-Zhuhai-Macau, Incheon; the game assigns jack-ups to water piers deeper than 6 m.

Related methods

Further reading

ISO 19905-1 · SNAME Technical Bulletin 5-5A · Noble Denton 0009/ND, Self-elevating platforms: guidelines for elevated operations