Construction methods · Caissons and marine foundations
Jack-up platforms
A barge with legs that are lowered to the seabed and then jack the hull above the waves, giving a steady drilling or piling deck in 5-40 m of water. Weather-independent once elevated, it is the platform behind most bored pile work at sea.
Also called: self-elevating platform, jack-up barge, SEP
Concept diagram (TheBridgeEng)
How it is done
Carry out a site-specific assessment (ISO 19905-1): leg penetration and punch-through risk from CPTs or borings at each location, seabed obstructions, scour, and metocean limits for moving and for the elevated condition.
Tow or self-propel to location in a weather window and position with GNSS, anchors or tugs.
Lower the legs to touchdown and pre-load each footing, by ballast water or leg by leg, to at least the largest reaction expected in the design storm, watching for sudden penetration. Hold point.
Jack the hull to the working air gap above the design wave crest.
Work from the deck (drilling, piling, cap formwork) within the deck-load and crane charts; re-check leg penetration and scour around the footings periodically.
Jack down, extract the legs (jetting where they are deep in clay) and move to the next pier.
Key numbers
Water depthabout 5–40 m for construction jack-ups; larger units to 60 m or more
Pre-loadat least the maximum footing reaction expected in the design storm
Air gaphull above the design wave crest with a margin, commonly at least about 1.5 m
Leg penetrationfrom under 1 m in dense sand to over 20 m in soft clay
Movesabout one day between piers in good weather
Where it fits
Bored piles, drilling investigation, pile caps and pier construction at sea and in estuaries; water 5-40 m.
Where it does not
Very soft seabeds with punch-through risk, rock outcrops, strong currents beyond the leg capacity.
Choosing it
Choose a jack-up over a floating barge for bored piling, caps and pier work at sea: drilling and concreting need a steady platform for days at a time.
Prefer a temporary trestle in water up to about 5–6 m along long viaducts, where land plant can work from it continuously.
Prefer floating plant for short tasks, for water deeper than the legs allow, or on soft seabeds with high punch-through risk.
For long campaigns at one large pylon, compare a fixed platform carried on the permanent casings, as at Sutong, which frees the jack-up for other piers.
Plant, pace and money
PlantJack-up 30-90 m with 100-300 t crane, legs to 60 m.
ProductivityMoves take a day; the deck then works around the clock.
CostUSD 20,000-80,000 per day; the game's jack-up rate.
Risks and controls
What goes wrong
Punch-through of a leg during preload (the major jack-up accident), leg damage, collision.
Quality assurance
Site-specific leg penetration assessment, preload records, weather limits enforced.
Origins
Self-elevating platforms were developed for offshore drilling in the Gulf of Mexico in the 1950s; construction jack-ups derived from them became the standard platform for marine piling and, later, offshore wind installation.
Examples
All Gulf sea bridges, Hong Kong-Zhuhai-Macau, Incheon; the game assigns jack-ups to water piers deeper than 6 m.