Construction methods · Bored piles and deep foundations

Drilled shafts (bored piles) with casing or slurry

A hole 0.8-3 m in diameter is drilled with a rotary rig, held open by a temporary casing or by bentonite or polymer slurry, then a cage is lowered and concrete placed by tremie. The universal heavy-load bridge foundation: pylons, river piers, urban viaducts, anything into rock.

How bridges get built · Bored piles and deep foundations · Drilled shafts (bored piles) with casing or slurry

Also called: bored pile, drilled shaft, cast-in-drilled-hole pile, CIDH

Drilled shafts (bored piles) with casing or slurry — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Set out the pile and build a working platform that can carry the rig and service crane; check for services and obstructions. At sea, install the piled platform or position the jack-up first.
  2. Install a temporary or permanent casing through the soft, loose or scourable upper soils (vibrated, oscillated or drilled in), plumb and sealed into a competent layer.
  3. Drill below the casing with augers and drilling buckets, under bentonite or polymer slurry where the ground is water-bearing or unstable, or dry in stable clay; keep the fluid level above the groundwater head at all times.
  4. Drill the rock socket with core barrels or rock augers to the level confirmed against the boring logs and the cuttings, logging every metre.
  5. Clean the base with a cleaning bucket or airlift, then check depth, verticality and base debris (weighted tape, sediment probe or camera) and test the slurry. This is the hold point before the cage goes in.
  6. Lower the cage with spacers and CSL tubes, hung so it cannot sink or float; place the concrete by tremie in one continuous pour with the pipe embedded, withdrawing any temporary casing as the concrete rises.
  7. Overpour, break down to sound concrete at cut-off, run CSL on every pile after about 3–7 days, and load test a sample pile in each ground type (static, bi-directional or rapid).

Key numbers

Where it fits

  • Loads of 5-50 MN per pile, rock sockets, boulders and cobbles, urban noise limits, river piers where driven piles would refuse; almost any site with a rig large enough.

Where it does not

  • Very loose sands under high water pressure without adequate slurry head (hole collapse).
  • Artesian layers (the game's blowout event) without casing through them.
  • Sites where a driven pile would simply be cheaper.

Choosing it

Plant, pace and money

PlantRotary drilling rig (100-400 kNm torque), casing oscillator or vibro-hammer, slurry plant and desanding, service crane, tremie equipment.
ProductivityOne 1.5 m pile of 30-40 m per rig per one to two days; deep rock sockets slow it to several days.
CostUSD 400-900 per metre for 1.5 m diameter on land; two to three times that from a jack-up at sea.

Risks and controls

What goes wrong

  • Base debris and soft toe, necking where the casing is withdrawn too fast, slurry contamination of the concrete, cage lifting during pouring, hole collapse. Every one of these is invisible until tested.

Quality assurance

Base cleanliness measured by sounding or sediment probe, slurry density and sand content before concreting, concrete volume against theoretical per pile, CSL on every pile, one static or O-cell test per pile type.

Origins

Machine-drilled shafts grew out of the hand-dug Chicago and Gow caissons of the 1890s and the truck-mounted augers adapted from oil-well drilling in Texas in the 1930s–40s. Bentonite support, introduced by Christian Veder for diaphragm walls in Italy in the 1950s, made deep uncased bored piles routine by the 1960s.

Examples

The default foundation for pylons and river piers on rock or deep soil: Sutong (131 piles of 2.5–2.8 m under each pylon), the Arthur Ravenel Jr. Bridge in Charleston and the Mumbai Trans Harbour Link. The game's reference picks it under pylons and river piers on rock.

Case studies

Sutong BridgeChina · 2008Each pylon stands on 131 bored piles of 2.8 m tapering to 2.5 m, 114–117 m long in sand and silt, under a 113.8 × 48.1 m cap; a verticality of 1:400 was achieved against a 1:200 limit.
Arthur Ravenel Jr. Bridge (Cooper River)USA · 20052.4 m shafts; lateral load tests showed a shaft with 25 mm permanent steel casing deflected less than half as much as a similar shaft built with temporary casing.
Mumbai Trans Harbour LinkIndia · 2024Typical marine foundations are four 2.2 m bored piles about 36.5 m long; the 21.8 km sea link is founded largely on large-diameter bored piles.

Related methods

Further reading

FHWA GEC 10 Drilled Shafts · EN 1536 (bored piles) · O'Neill and Reese · O'Neill and Reese (1999), Drilled Shafts: Construction Procedures and Design Methods (FHWA-IF-99-025) · ADSC/DFI Drilled Shaft Inspector's Manual · Fleming, Weltman, Randolph and Elson, Piling Engineering · ICE Specification for Piling and Embedded Retaining Walls (SPERW)