Construction methods · Steel erection

Cantilever erection of steel (derrick and lifting frames)

Steel trusses and box girders are built outward from a pier as a cantilever, each new piece lifted by a derrick or creeper crane that rides on the already-erected structure. The great method of cantilever trusses and of long-span steel over navigable water; still used for trusses and for the main spans of cable-supported steel decks.

How bridges get built · Steel erection · Cantilever erection of steel (derrick and lifting frames)

Also called: cantilever steel erection, creeper crane, derrick crane erection, traveller erection of steel

Cantilever erection of steel (derrick and lifting frames) — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Erect the pier-head unit (or the anchor span on falsework) and fix it to the pier with temporary ties or stability towers so it can resist the out-of-balance moment of the cantilever.
  2. Install the creeper crane, derrick or deck crane on the erected steel and set up delivery: barges moored below, or trolleys along the completed deck.
  3. Cycle: lift the next member or segment, pin and bolt it (or weld, for boxes) with enough fasteners to carry the next stage before release, then advance the crane by one panel.
  4. Keep the two cantilevers within the allowed out-of-balance load, or tie the cantilever back to an anchor span or temporary backstays; add temporary stays or a king post where the free cantilever would be too long.
  5. Survey tip level and line after every panel at a reference temperature and correct camber at the joints or with temporary jacks.
  6. Close at midspan by jacking the tips (or adjusting backstays) to match the closure gap at the planned temperature, or by lowering a suspended span between the tips.
  7. Remove cranes, temporary ties and jacks, convert the structure to its final support system and survey the as-built profile.

Key numbers

Where it fits

  • Steel trusses of 150-500 m, box girder main spans over navigation routes, steel arches erected as cantilevers with tie-backs, cable-stayed steel decks.

Where it does not

  • Sites where a floating crane can lift the whole span in one go; short spans.

Choosing it

Plant, pace and money

PlantDerrick or creeper cranes (100-500 t), barges, temporary tie-backs, jacking systems for closure.
ProductivityOne panel (10-15 m) per two to five days per cantilever.
CostErection USD 800-1,500 per tonne.

Risks and controls

What goes wrong

  • Overturning of the cantilever, connection slip, closure misfit from temperature, crane derailment (the 1907 Quebec Bridge collapse remains the lesson).

Quality assurance

Stage-by-stage analysis with temporary conditions, daily survey of the tip, bolt inspection, closure at the planned temperature.

Origins

Cantilever erection of steel trusses was established on the Forth Bridge (1890), whose double cantilevers were built out from the towers without falsework. The Quebec Bridge collapses of 1907 (during cantilever erection) and 1916 (when the suspended span fell while being lifted) made erection-stage analysis a discipline in its own right.

Examples

Forth Bridge, Quebec Bridge (completed 1917), Japanese Minato Bridge, Chinese Yangtze truss bridges.

Case studies

Forth BridgeUK · 1890Two 521 m main spans built as balanced cantilevers out from three towers, with the central girders built out from the arm tips and joined; the classic cantilever truss erection.
Quebec BridgeCanada · 1917549 m cantilever span, still the longest. In 1907 the south arm collapsed during cantilever erection when compression chords buckled (75 deaths); in 1916 the suspended span fell while being jacked up (13 deaths).
Sydney Harbour BridgeAustralia · 1932503 m steel arch built as two cantilevered halves by creeper cranes travelling on the upper chords, each half held back by cables anchored in horseshoe-shaped tunnels; the halves met in August 1930.
Cleddau Bridge, Milford HavenUK · 1970 (collapse), 1975 (completed)A steel box girder span being cantilevered from a pier collapsed in June 1970 (four deaths). With the West Gate (1970) and Koblenz (1971) collapses it led to the Merrison rules for steel box girders.

In the bridge game

What Bridge Master applies when you pick it

Deck types: Steel truss, Steel box girder, Orthotropic steel box, Steel arch, Cable-stayed, Extradosed, Steel plate girder. Spans 100-300 m, up to 550 m.

  • +30: Long steel truss or arch: cantilever erection.
  • +15: Keeps the channel open.
  • -30: Simpler methods.
  • +10: Tall piers: no falsework or bents, everything comes from the finished deck.
  • -10: Long free cantilevers in strong wind: temporary stays and a wind study of the stages.

Try it in the game →

Related methods

Further reading

Troitsky, Cable-stayed Bridges · Japanese steel bridge erection standards · Durkee, Steel Bridge Construction (chapter in Chen and Duan, Bridge Engineering Handbook) · Merrison Committee, Inquiry into the Basis of Design and Method of Erection of Steel Box Girder Bridges (1973)