Construction methods · Steel erection

Crane erection of steel girders

Plate girders, box girder sections or truss members are lifted by mobile or crawler cranes from the ground or a trestle onto the piers and temporary supports, then spliced. With ground access it is the simplest steel method and spans to 90 m with temporary towers or by lifting pre-assembled units.

How bridges get built · Steel erection · Crane erection of steel girders

Also called: piece-by-piece erection, crane placement of steel, girder erection

Crane erection of steel girders — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Prepare the erection engineering before any steel arrives: a stage-by-stage stability check of each girder line, a lift plan for every pick (crane, radius, rigging, ground bearing) and the temporary bracing and guying scheme.
  2. Build crane pads and access, verify ground bearing under crawler tracks or outrigger mats, and stage the girders in erection order with splice plates and bolts at hand.
  3. Lift the first girder onto the bearings or tower heads and hold it with the crane (or a holding crane) until it is restrained by guys, shoring or a connection to a second girder; a single unbraced girder is the most critical stage of the job.
  4. Set the next girder and connect the cross-frames or diaphragms before releasing the cranes, so each pair forms a torsionally stable unit; where crane capacity allows, pre-assemble pairs with their bracing on the ground and lift them as one unit.
  5. Make field splices in the air on temporary towers or with strongbacks, filling about half the holes with drift pins and bolts before the crane lets go of a spliced piece.
  6. Complete all cross-frames and lateral bracing, check line, level and web plumbness, then tension the bolts in the specified sequence.
  7. Release the temporary towers once the girders act continuously and place the deck in the analysed pour sequence, monitoring deflections against the predicted camber.

Key numbers

Where it fits

  • Overpasses, valley bridges with road access, spans 30-90 m, steel arches and trusses assembled on the ground and lifted as units.

Where it does not

  • Piers in water without a trestle, unstable single girders left unbraced, heavy units beyond crane charts at the required radius.

Choosing it

Plant, pace and money

PlantCrawler cranes 250-1,200 t, tandem lifts, temporary towers, bolting crews.
ProductivityOne to three days per span for plate girders; longer for trusses.
CostErection USD 300-600 per tonne; deck USD 1,400-2,200 per m2 in place.

Risks and controls

What goes wrong

  • Girder lateral-torsional instability before bracing (several collapses), tandem lift coordination, ground failure under outriggers.

Quality assurance

Erection engineering with stability check at every stage, lift plans, bolt tension inspection.

Origins

Derricks and guy-derricks erected steel girders until mobile and crawler cranes took over after the Second World War. Erection-stage stability is now a formal design check set out in the AASHTO/NSBA Steel Bridge Erection Guide Specification; failures such as the State Route 69 Tennessee River collapse (1995) showed why.

Examples

The game's steel approach spans; most US and European steel overpasses.

Case studies

State Route 69 Tennessee River Bridge, CliftonUSA · 1995Two completed spans of a three-span haunched plate girder unit (about 104 + 160 + 104 m) fell into the river during erection: missing and partly bolted cross-frames left a compression flange unbraced and it buckled laterally. A standard lesson on bracing the first girder lines.
Marcy Pedestrian BridgeUSA · 2002A single steel trapezoidal tub girder twisted and collapsed during the concrete deck pour because the open section lacked adequate top lateral bracing; one worker died. Shows that tub girders are torsionally weak until the top flanges are braced or the deck has cured.

In the bridge game

What Bridge Master applies when you pick it

Deck types: Steel plate girder, Steel box girder, Steel truss, Orthotropic steel box, Steel arch, PSC I-girder, PSC U-girder, Spliced PSC girder, Network tied arch. Spans 20-60 m, up to 90 m.

  • +25: Standard steel erection.
  • +20: Light lifts in short windows.
  • -35: Use barges or launching.
  • -20: Reach limits; launching.
  • -20: Over about 60 m a single lift needs a huge crane; use temporary bents.
  • -40: Water under the span: a ground crane needs a trestle or crane barges here; launching or a floating crane is the usual answer.
  • not allowed: Land crane erection over deep water.

Try it in the game →

Related methods

Further reading

AASHTO/NSBA Steel Bridge Erection Guide Specification · AISC Steel Construction Manual · AASHTO/NSBA S10.1 Steel Bridge Erection Guide Specification · NCHRP Report 725, Guidelines for Analysis Methods and Construction Engineering of Curved and Skewed Steel Girder Bridges · FHWA, Engineering for Structural Stability in Bridge Construction