Construction methods · Steel erection

Truss assembly and erection

Trusses are assembled from chords, diagonals and verticals joined at panel points with gusset plates. They can be built on falsework, cantilevered out panel by panel, assembled whole on the bank and floated or slid in, or lifted in sections. The geometry must close: trusses are unforgiving of accumulated error.

How bridges get built · Steel erection · Truss assembly and erection

Also called: truss erection, panel-point erection, truss bridge construction

Truss assembly and erection — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Fabricate members with connection holes drilled to a verified geometry: full or progressive shop trial assembly, or CNC drilling from a checked 3D model, so the panel points close in the field.
  2. Choose the erection scheme from the site: on falsework towers for short or land spans, by cantilever from the piers with creeper or derrick cranes for long spans, or assembled whole on shore and floated, slid or lifted in.
  3. Set the bearings and first panels, then erect panel by panel (bottom chord, verticals and diagonals, top chord) so each triangle is closed before the next is started.
  4. Pin and bolt each panel point to the required fill of drift pins and bolts before load passes through it, and complete lateral and sway bracing as erection proceeds.
  5. Survey camber, line and panel-point levels at a reference temperature after each stage; correct with jacks at temporary supports rather than by forcing connections.
  6. Install the floor system (floor beams, stringers or orthotropic deck) and the deck, then release temporary supports in the analysed order.
  7. Close the last panel or the midspan joint at the planned temperature, tension all bolts and inspect gussets and connections.

Key numbers

Where it fits

  • Rail bridges, long-span river crossings, sites where the deck must be shallow for clearance, floating or sliding in complete trusses.

Where it does not

  • Sites without room for assembly or without lifting capacity; highly repetitive short spans where girders are cheaper.

Choosing it

Plant, pace and money

PlantCranes, derricks, temporary towers, bolting crews.
ProductivityOne panel per day on towers; slower by cantilever.
CostSteel USD 4,000-8,000 per tonne fabricated and erected.

Risks and controls

What goes wrong

  • Gusset plate deficiencies (I-35W), member buckling during erection, misfit at closure.

Quality assurance

Shop trial assembly, gusset design check, bolting inspection, survey.

Origins

Truss forms were systematised in the 1840s (Howe, Pratt and Warren patents) and steel trusses dominated long railway spans until the mid-20th century. Lindenthal's Sciotoville Bridge (1917) introduced large continuous trusses; Ikitsuki (1991) holds the record continuous truss span of 400 m.

Examples

Ikitsuki (400 m continuous truss), Japanese and Chinese rail-road trusses, US Mississippi trusses.

Case studies

Sciotoville BridgeUSA · 1917Gustav Lindenthal's two-span continuous railway truss over the Ohio River (two spans of about 236 m), the first large continuous truss.
Astoria–Megler BridgeUSA · 1966376 m continuous truss main span over the Columbia River, the longest continuous truss span in North America.
Ikitsuki BridgeJapan · 1991400 m main span, the longest continuous truss span in the world.
I-35W Mississippi River BridgeUSA · 1967 (collapsed 2007)Deck truss whose U10 gusset plates had been designed about half as thick as needed; with added dead load and construction materials on the deck, they failed. The NTSB investigation led to FHWA guidance on load rating gusset plates.

Related methods

Further reading

AASHTO LRFD 6 · NCHRP gusset plate guidance · NTSB Highway Accident Report HAR-08/03 (I-35W collapse) · FHWA, Load Rating Guidance and Examples for Bolted and Riveted Gusset Plates in Truss Bridges