Construction methods · Precast concrete decks

Crane erection of precast girders

Precast I, U or bulb-T girders are lifted from the truck onto the pier caps by one or two mobile or crawler cranes standing beside the bridge, then a deck slab is cast on top. The most common bridge construction on earth for spans of 20-45 m wherever a crane can stand.

How bridges get built · Precast concrete decks · Crane erection of precast girders

Also called: crane placement, girder erection by crane, tandem lift

How it is done

  1. Prepare a lift plan for every span: heaviest girder at its radius, crane configuration, ground bearing pressure under tracks or outriggers (with mats), exclusion zones and the road or rail closures needed.
  2. Check the bearings for level and position, and inspect girders on delivery for camber, sweep, end-zone cracks and handling damage.
  3. Lift with one crane, or two in tandem, using the specified lifting points or a spreader, control swing with tag lines and stop at the wind limit in the lift plan.
  4. Land the girder on its bearings and brace it before the crane releases: the first girder of each span needs external bracing to the pier cap, and the next ones are tied to it.
  5. Repeat across the width, then install the end and intermediate diaphragms and permanent bracing; check girder stability under wind until the deck is cast.
  6. Survey the girder tops and calculate the haunch (build-up) for the deck profile, allowing for camber growth.
  7. Form and cast the deck slab and any continuity diaphragms, and remove temporary bracing only when the design allows.

Key numbers

Where it fits

  • Overpasses, viaduct approaches, river bridges from the banks or a trestle, spans to about 45-50 m (55 m with two cranes), any site with crane access on both sides.

Where it does not

  • Piers in water without a trestle or barge, heights over 30-40 m (crane capacity falls with radius), sites where girder transport cannot reach.

Choosing it

Plant, pace and money

PlantCrawler crane 250-600 t (or two), transport, bracing, deck formwork.
ProductivityOne to three days per span; a girder every 30-60 minutes once set up.
CostDeck USD 800-1,300 per m2; among the cheapest.

Risks and controls

What goes wrong

  • Girder rollover before bracing (a recurring fatal accident), crane tipping on soft ground, lifting in wind, crane outriggers on the edge of an excavation.

Quality assurance

Lift plan for each span with ground bearing checks, bracing installed before the crane releases, girder camber checked before placing the slab.

Origins

Prestressed concrete girders reached the US with the Walnut Lane Memorial Bridge in Philadelphia (1950); the AASHO-PCI standard I-girders of the late 1950s and the bulb-tees of the late 1980s made precast girders erected by crane the default for short and medium spans.

Examples

The game's default approach-span method; most Korean, US and European highway bridges.

Case studies

Puyallup River Bridge (southbound I-5), Tacoma, WashingtonUSA · 202168 m (223 ft) WF100 girders, the longest prestressed concrete girders in the US at the time, trucked a few kilometres from the plant and lifted at night in windows coordinated with two railways.
Lake Pontchartrain Causeway, LouisianaUSA · 1956About 38 km of identical precast prestressed spans mass-produced on shore and set by floating cranes, an early demonstration of assembly-line precast erection.

In the bridge game

What Bridge Master applies when you pick it

Deck types: PSC I-girder, PSC U-girder, Voided slab, Spliced PSC girder, Timber deck, FRP deck, Precast segmental box, RC slab, Steel plate girder, Steel box girder. Spans 20-45 m, up to 60 m.

  • +25: Cranes can stand at the piers: just lift them in.
  • +15: Night lifts from the verge or in a possession.
  • -40: Cranes cannot stand in water; launcher or barge.
  • -30: No crane positions; use a launching girder.
  • -25: Tall piers exceed reach; launcher.
  • -20: Very heavy girders need large tandem cranes.
  • -40: Water under the span: a ground crane needs a trestle or crane barges here; a launcher or floating crane is the usual answer.
  • not allowed: Land crane erection over deep water.