Construction methods · Heavy lift, moving and accelerated construction

Lateral slide (slide-in bridge construction)

The new bridge is built beside the existing one on temporary supports, the old bridge is demolished in a short closure, and the new one is slid sideways onto the permanent supports on PTFE pads with jacks. Traffic loses a weekend instead of a year.

How bridges get built · Heavy lift, moving and accelerated construction · Lateral slide (slide-in bridge construction)

Also called: slide-in, lateral launching, bridge slide, SIBC

Lateral slide (slide-in bridge construction) — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Plan the closure and the slide: slide distance, friction assumptions (PTFE on stainless steel or greased skid beams), push or pull system, deck stresses when supported only at the slide shoes, and contingency for a stuck slide.
  2. Build temporary supports beside the existing bridge with slide tracks continuous from the temporary to the permanent substructure.
  3. Build the new superstructure on the temporary supports at final level, complete with deck, barriers and sometimes surfacing; at the same time build or modify the permanent substructure under or beside the old bridge.
  4. In the closure, demolish the old superstructure or slide it out, sometimes onto temporary supports for later removal.
  5. Push or pull the new superstructure across with synchronised jacks or strand jacks at a few metres per hour, keeping both ends in step and monitoring skew and drift by survey and stroke counters.
  6. Jack the deck off the slide shoes, remove the shoes and set it on its bearings; complete approach slabs and joints and reopen.
  7. Remove the temporary supports and slide tracks after reopening.

Key numbers

Where it fits

  • Replacements of bridges over live roads, railways and rivers; spans 30-120 m; single or multi-span decks built at the final level.

Where it does not

  • Sites without room beside the alignment; decks too flexible to slide without distortion; skewed slides without engineering.

Choosing it

Plant, pace and money

PlantTemporary supports, slide tracks and PTFE, jacks, survey.
ProductivityMonths beside the road; 24-72 hours of closure.
Cost10-30 % above conventional construction for the temporary works; recovered in user-delay cost.

Risks and controls

What goes wrong

  • Differential friction racking the deck, track misalignment, jacks out of sync, weather during the closure.

Quality assurance

Trial slide over a short distance, synchronised jack control, survey at intervals during the slide.

Origins

Sliding new spans sideways into position has long been used for railway bridges in Europe (the German 'Querverschub'); in the US the FHWA promoted it as slide-in bridge construction in the 2010s, with the Utah DOT among the first and most frequent users.

Examples

Utah DOT slide-ins (dozens since the late 2000s), I-5 Skagit River (2013), Sellwood (2013), Milton–Madison (2014), UK railway bridge replacements, Korean railway crossings.

Case studies

I-5 Skagit River BridgeUSA · 2013After a truck strike brought down a truss span in May, temporary modular spans carried traffic; the new 49 m precast girder span (about 820 t), built alongside, was slid onto the piers on 14–15 September in about 19 hours.
Sellwood Bridge, PortlandUSA · 2013The old steel truss was slid about 20 m north onto temporary piers to serve as the detour while the new bridge was built on the original alignment.
Milton–Madison BridgeUSA · 2014The new Ohio River truss, built on temporary piers beside the old bridge, was slid about 17 m sideways onto the rehabilitated piers, one of the longest lateral slides undertaken.

In the bridge game

What Bridge Master applies when you pick it

Deck types: Steel plate girder, Steel box girder, PSC I-girder, PSC box (cast in place), Steel truss, Orthotropic steel box, Steel arch, PSC U-girder, Spliced PSC girder, Voided slab, Precast segmental box, Network tied arch. Spans 30-100 m, up to 150 m.

  • +30: Replace or cross in one possession: slide it in.
  • -35: No reason to slide over open ground.
  • -20: Sliding a deck over 100 m: huge temporary supports; ILM or cantilever instead.
  • -25: A one-off operation for one span: on a multi-span viaduct it is the exception for the main span, not the method for the deck.

Try it in the game →

Related methods

Further reading

FHWA Slide-In Bridge Construction Implementation Guide · AASHTO ABC Guide Specifications