Construction methods · Piers, pylons and abutments

Steel and composite pylons

Pylons fabricated as steel boxes in sections of 10-20 m, lifted by tower or floating cranes and bolted or welded, sometimes over a concrete lower part. Faster than concrete above the deck, lighter on the foundation, and dependent on lifting capacity and fabrication precision.

How bridges get built · Piers, pylons and abutments · Steel and composite pylons

Also called: steel tower, composite pylon, stainless-clad pylon

Steel and composite pylons — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Fabricate the tower in blocks with machined end faces and trial-assemble adjacent blocks in the shop to check straightness, twist and splice fit.
  2. Set the base: anchor bolts or an anchor frame cast into the pier, a grouted base plate and a survey of base level and position, since every block above follows it.
  3. Lift the lower blocks with a floating or crawler crane and the upper blocks with a climbing crane attached to the tower; make the field splices with pretensioned high-strength bolts or site welds.
  4. Survey each block for verticality and twist, correct only within the limits of the splice details, and track the cumulative tilt against the erection analysis.
  5. Fit temporary dampers or tuned mass dampers to control vortex-induced vibration of the free-standing tower until cables or stays restrain it.
  6. Erect cross beams and integral stay anchor boxes with the shafts, inspecting welds and bolt tension at each level.
  7. Commission dehumidification of the closed cells, touch up coatings, install lifts and access, and dismantle the climbing crane from the top.

Key numbers

Where it fits

  • Suspension bridge towers, cable-stayed pylons where speed or foundation load matters, seismic regions (ductile steel), sites with a fabrication yard and heavy lift.

Where it does not

  • Sites without heavy lift access; budgets sensitive to steel prices; humid marine sites without a maintenance plan for coatings.

Choosing it

Plant, pace and money

PlantFabrication yard, tower crane 30-100 t or floating crane 1,000-3,000 t, welding and bolting crews.
ProductivityA segment every one to three days; a 200 m tower in 4-8 months.
CostUSD 8,000-15,000 per tonne erected.

Risks and controls

What goes wrong

  • Fit-up errors between segments, weld defects, wind during lifts, corrosion inside closed boxes.

Quality assurance

Machined end inspection, survey per segment, weld NDT, dehumidification of closed cells.

Origins

Steel towers were the norm for suspension bridges from the riveted cellular towers of the Golden Gate (1937) to the welded towers of Akashi Kaikyo (1998); outside Japan, concrete took over most long-span towers from the 1980s.

Examples

Akashi Kaikyo, Golden Gate and most suspension towers; Stonecutters top sections; Japanese cable-stayed bridges with steel pylons.

Case studies

Golden Gate BridgeUSA · 1937Riveted cellular steel towers 227 m high, the classic American suspension-tower construction.
Akashi Kaikyo BridgeJapan · 1998298 m welded steel towers erected block by block with a climbing crane; tuned mass dampers controlled wind-induced vibration of the free-standing towers.
Tatara BridgeJapan · 1999Steel pylons over 200 m high for an 890 m span, the longest cable-stayed span when opened.

Related methods

Further reading

AASHTO LRFD 6 · Japanese Honshu-Shikoku Bridge Authority standards