Construction methods · Heavy lift, moving and accelerated construction
Floating crane erection
A crane barge of 1,000-4,000 t lifts complete spans, steel box sections, arch halves or pylon segments from a delivery barge and sets them on the piers. Where the water is deep enough and calm enough, it replaces months of piece-by-piece erection with days of lifts.
Also called: floating sheerleg, crane vessel, whole-span lift
Concept diagram (TheBridgeEng)
How it is done
Plan the marine operation: lift weights with contingency, rigging design, crane capacity at the required outreach, water depth along the route and at the piers, moorings or dynamic positioning, and wind, wave and current limits with go/no-go points.
Prepare the piers with bearings or temporary seats, guides or bumpers, and survey the landing positions.
Fabricate the units in a yard on the water, load them out onto a delivery barge (skidding, SPMT or by the crane itself) and sea-fasten them.
Mobilise the crane vessel, moor it at the lift position, check vessel stability and ballast for the lift, and trial the rigging.
Lift within the agreed window, allowing for dynamic amplification; slew or move the vessel to the pier and lower the unit onto its guides under tag-line or winch control.
Set the unit on its bearings, make temporary fixings, release the rigging and survey; connect units (stitch pours, splices, wet joints) before the next weather event.
Reposition for the next lift or demobilise, keeping a record of each lift against the plan.
Key numbers
Crane vessels for bridge worktypically 1,000–4,000 t capacity; purpose-built catamaran vessels have set girders of about 7,500 t (Confederation Bridge)
Water depthusually 6 m or more along the route and at the piers
Dynamic amplification factor in lift designabout 1.1–1.3 depending on load and exposure (DNV-ST-N001)
Spans lifted wholecommonly 50–200 m
Rateone to three lifts per day in good weather
VesselUSD 100,000–400,000 per day (indicative)
Where it fits
Sea and estuary viaducts with whole precast spans (typically to 3,000 t; purpose-built catamaran cranes have set 7,500 t girders), steel box girder main span sections, pylon tops, arches assembled on shore; water deep enough for the vessel (usually 6 m or more).
Where it does not
Shallow rivers, strong currents, exposed sites without weather windows, lifts beyond the crane class (the game's marine_lift check), long spans beyond about 200 m in one piece.
Choosing it
Choose it over piece-by-piece erection for long marine viaducts with many identical spans: whole-span lifts move the work into a yard.
Prefer strand jacks from the structure above (suspension decks) or from the piers when the unit is too heavy or the water too shallow for a crane vessel.
Prefer float-in with ballasted barges when the span is heavier than any available crane but can be floated under the piers at a suitable tide.
Avoid it where weather windows are short and unpredictable; downtime on a vessel costing hundreds of thousands of dollars a day decides the economics.
Plant, pace and money
PlantSheerleg or revolving crane vessel 1,000-4,000 t, delivery barges, tugs, anchor handling.
ProductivityOne to three lifts per day in good weather.
CostUSD 100,000-400,000 per day for the vessel; the game's floating crane mobilisation.
Risks and controls
What goes wrong
Vessel motion during the lift, rigging failure, collision with the pier, weather downtime.
Quality assurance
Lift plan with dynamic amplification, rigging certificates, weather and tide limits with go/no-go criteria.
Origins
Sheerleg crane barges were used for bridge spans through the 20th century; purpose-built heavy-lift vessels for whole precast spans arrived with the Great Belt West Bridge in the early 1990s, whose 110 m spans were set by the catamaran crane Svanen, later used for Confederation Bridge.
Examples
Great Belt West and Confederation Bridge (whole concrete spans set by Svanen), Øresund approach spans, Gateshead Millennium Bridge, Hong Kong–Zhuhai–Macao Bridge, Incheon Bridge approaches, the Tappan Zee replacement.
Case studies
Great Belt West BridgeDenmark · 1994Precast concrete box girder spans of 110 m set whole by the catamaran crane vessel Svanen.
Confederation BridgeCanada · 199712.9 km crossing; precast main girders up to about 7,500 t and 192.5 m long set by the heavy-lift vessel Svanen.
Gateshead Millennium BridgeUK · 2001The complete tilting arch bridge, about 850 t, was lifted into place in one piece by the floating crane Asian Hercules II in November 2000.
Governor Mario M. Cuomo Bridge (Tappan Zee replacement)USA · 2017–2018The large floating crane I Lift NY (originally the Left Coast Lifter) set pre-assembled steel girder spans for the twin crossings.
In the bridge game
What Bridge Master applies when you pick it
Deck types: PSC I-girder, PSC U-girder, Precast segmental box, Steel box girder, Orthotropic steel box, Steel truss, Steel arch, Spliced PSC girder, Steel plate girder, Voided slab, Extradosed, Cable-stayed, Network tied arch. Spans 40-120 m, up to 200 m.
+30: Deep water viaduct: lift whole spans by floating crane.
+15: Navigable river with barge access.
-45: Crane barge cannot float.
-25: Fast current makes barge positioning dangerous.
+10: Floating plant is the way in when trestles and cofferdams are banned.
not allowed: Floating crane on dry land.
not allowed: A floating crane needs water under the span.