Construction methods · Piers, pylons and abutments

Pylon construction: concrete, anchorage zones and geometry

A pylon is a tall pier with a cable anchorage zone at the top: the concrete legs climb with jump forms, the cross beams are cast on brackets or lifted as steel, and the stay anchorages are steel boxes or corrugated pipes embedded in a congested, heavily post-tensioned zone. Geometry control is the whole game: the pylon must be where the cables expect it.

How bridges get built · Piers, pylons and abutments · Pylon construction: concrete, anchorage zones and geometry

Also called: tower construction, cable-stayed pylon, pylon anchor box

Pylon construction: concrete, anchorage zones and geometry — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Set up the survey control: reference stations off the structure, total stations and GNSS on the pylon, and temperature sensors, so every lift can be corrected for sun, wind and shortening.
  2. Climb the legs in 4–5 m lifts with climbing formwork; on inclined legs install temporary horizontal struts, often jacked to a preset force, to limit bending until the cross beams are built.
  3. Cast the cross beams on brackets or falsework supported from the legs, or lift prefabricated steel beams; stress their post-tensioning and release the temporary struts in the designed order.
  4. Build the legs to a construction geometry offset from the final shape by the predicted elastic, creep and shrinkage shortening and by the deflection the stays will cause.
  5. In the anchorage zone, set the steel anchor boxes or embedded guide pipes lift by lift, surveying each anchorage point and pipe axis before concreting.
  6. Where the anchorage zone relies on concrete, install and stress the horizontal post-tensioning (straight or loop tendons) that carries the stay forces around the section.
  7. Complete the head (top anchorages or saddles, lightning protection, aviation lights, maintenance lift and access) and strike the climbing system.
  8. Keep surveying through deck erection and stay tensioning so the as-built pylon position feeds the stay length and force calculations.

Key numbers

Where it fits

  • Concrete pylons of 60-300 m; H, A, inverted-Y and diamond shapes.

Where it does not

  • Skipping the temporary ties on inclined legs; skipping the lift-by-lift survey.

Choosing it

Plant, pace and money

PlantClimbing forms, tower crane of 100-300 m hook height, concrete pump with placing boom, survey with prisms and GNSS.
Productivity8-14 months for a 150-200 m pylon per leg pair.
CostUSD 30-120 million per pylon depending on height.

Risks and controls

What goes wrong

  • Geometry error accumulating (cables then need adjustment), cracking in the anchorage zone, wind on the free-standing legs before the cross beam, crane capacity for the anchor boxes.

Quality assurance

Daily survey with temperature correction, anchor box position within 5-10 mm, post-tensioning records.

Origins

Concrete towers for cable-stayed bridges go back to Morandi's Maracaibo bridge (1962); steel anchor boxes embedded in concrete pylons became the usual solution for large stay forces from the 1990s, as on the Pont de Normandie (1995).

Examples

Sutong (306 m), Russky (320 m), Incheon (238 m), Stonecutters (298 m, composite top).

Case studies

Pont de NormandieFrance · 1995Inverted-Y concrete pylons about 215 m high for an 856 m span, a world record for cable-stayed bridges when opened.
Sutong BridgeChina · 2008Concrete pylons 306 m high for a 1,088 m cable-stayed span, the longest when opened.
Stonecutters Bridge, Hong KongChina · 2009Single-leg towers 298 m high: concrete in the lower part, composite with a stainless steel skin in the upper part where the stays anchor.

Related methods

Further reading

Gimsing and Georgakis, Cable Supported Bridges · PTI DC45.1 Recommendations for Stay Cable Design · fib Bulletin 30, Acceptance of stay cable systems using prestressing steels