Construction methods · Driven piles

Steel pipe piles (open- and closed-ended)

Steel tubes 400-2,500 mm in diameter, driven open-ended (the soil plug carries part of the base) or closed with a shoe (full displacement), spliced by welding to any length. High bending capacity, ideal in water, for scour and ship impact, and for liquefaction; the standard marine pile of Japan and Korea.

How bridges get built · Driven piles · Steel pipe piles (open- and closed-ended)

Also called: tubular steel pile, steel pipe pile, plugged pile

How it is done

  1. Specify diameter, wall thickness, grade and seam type, the toe reinforcement or shoe, and the corrosion allowance; run a wave equation driveability study that includes plugged and unplugged behaviour.
  2. Set up the pile barge or jack-up with a template or pile gate that holds position and rake, and survey each pile before and during driving.
  3. Drive the upper part by vibro-hammer where allowed, then by impact hammer; record blows, energy and penetration continuously.
  4. Splice with full-penetration girth welds after checking fit-up and alignment, and test them ultrasonically before driving resumes; keep splices out of the zone of maximum bending.
  5. Open-ended piles: measure the soil plug; where it does not form or soft soil fills the tube, clean out and cast a concrete plug or close the toe. Closed-ended piles: check for water ingress.
  6. Drive to the required set and penetration; test dynamically at end of driving and on restrike, and by static or bi-directional load test where the design requires.
  7. Cut off to level, clean out the head and cast a reinforced concrete plug for the cap connection (or weld a head plate), then repair coatings in the splash zone.

Key numbers

Where it fits

  • River, estuary and sea piers; long piles through soft clay to a deep layer; pylon foundations in sand; sites with lateral load from ships, ice or earthquakes.

Where it does not

  • Rock at the tip without a socket (use PRD or bored piles), highly corrosive ground without protection.

Choosing it

Plant, pace and money

PlantBarge with template, hydraulic hammer 15-40 t, welding crews, ultrasonic testing.
Productivity2-6 piles of 40-60 m per barge per shift including splices.
CostUSD 250-600 per metre for 1,000-1,200 mm including driving; steel price dominates.

Risks and controls

What goes wrong

  • Buckling or tearing of the toe on boulders, running in soft layers, and corrosion: allow a sacrificial thickness from EN 1993-5 or the local port standard (in temperate seawater about 3.5 mm per 100 years where permanently immersed and about 7.5 mm in the splash and low-water zone), and add coatings and cathodic protection in the splash zone.

Quality assurance

Weld inspection, driving records and PDA, verticality survey by template, plug measurement.

Origins

Steel pipe piles became the standard marine foundation with offshore oil platforms in the Gulf of Mexico from the late 1940s and with Japanese port and bridge works from the 1960s, as large hammers and spiral-welded pipe made long, large-diameter piles economic.

Examples

Long marine viaducts in China (Donghai, Hangzhou Bay), seismic bay crossings (San Francisco-Oakland Bay Bridge Skyway) and soil reinforcement under gravity foundations (Rion-Antirion); the reference uses open-ended pipes for water piers over sand.

Case studies

San Francisco-Oakland Bay Bridge East Span (Skyway)USA · 2013Piers on raked steel pipe piles 2.5 m in diameter and up to about 100 m long, driven at a batter of about 1:6 through soft Bay mud with a hydraulic hammer of about 1,700 kJ.
Rion-Antirion BridgeGreece · 2004Steel pipes 2 m in diameter and 25-30 m long were driven at 7-8 m spacing under the 90 m pier footings as soil-reinforcing inclusions, deliberately not connected to the footings, to strengthen weak seismic seabed soils.
Donghai BridgeChina · 2005The 20 km deep-sea section rests on groups of raked steel pipe piles driven from piling barges and capped by precast concrete boxes.
Hangzhou Bay BridgeChina · 2008Steel pipe piles with precast piers carry the approach spans, about 95 % of the 36 km crossing, in strong tidal currents.

Related methods

Further reading

API RP 2A · JIS A 5525 · Eurocode 3-5 · API RP 2GEO Geotechnical and Foundation Design Considerations · EN 1993-5 Piling (Table 4-2 corrosion rates)