Construction methods · Shallow foundations, cofferdams and dewatering
Precast and floating cofferdam boxes
Instead of driving sheet piles, a steel or precast concrete box is floated to the pier, lowered onto pre-installed piles or the bed, and pumped dry. It doubles as the permanent pile-cap formwork and removes divers and cofferdam bracing from the critical path.
Also called: floated-in cofferdam, precast concrete cofferdam, steel box cofferdam
Concept diagram (TheBridgeEng)
How it is done
Install the foundation piles first (from a jack-up, trestle or pile barge), cut them to level and survey their as-built positions; the box openings are made to suit.
Fabricate the box in a yard: a steel or precast concrete floor with pile openings and walls high enough for the design tide and waves; steel boxes for large caps are often double-walled so they can be ballasted.
Transport by barge or floating crane, or float the box itself; lower it over the pile heads with strand jacks or a crane, or hang it from brackets or hangers on the piles (perched or suspended box).
Seal the gap between each pile and its opening with rubber collars, steel sleeves and an underwater concrete or grout plug; seal the floor joints.
Hold point: pump the box down and leak-test it before any reinforcement is placed; repair leaks from inside.
Fix reinforcement and cast the cap in the dry, the box acting as formwork; transfer the load to the piles before releasing the hangers or jacks.
Leave the box as permanent formwork and impact protection, or strip removable wall panels for reuse on the next pier.
Key numbers
Water depthtypically 5-25 m, with the cap near or above low water.
Box weighthundreds of tonnes for viaduct caps; several thousand tonnes for pylon caps (a single 5,000 t steel box at Sutong).
Pile openingstypically oversized by 100-300 mm to absorb pile position tolerance, the gap sealed by collars and grout.
Cyclesetting in one or two tidal windows; cap cast within 1-3 weeks of setting.
Where it fits
Sea and estuary piers with pile groups in 8-25 m of water, where sheet piles cannot be driven or would take too long.
Where it does not
Sites without a fabrication yard or towing route; small piers where a sheet-pile cofferdam is cheaper.
Choosing it
Choose a box over a sheet-pile cofferdam when the cap sits at or above the bed, the water is deep or tidal, the bed holds riprap or boulders, or many identical caps justify a casting yard.
Prefer a sheet-pile cofferdam and a low cap below the bed when ship impact, scour or hydraulic blockage require the cap to be buried.
A perched or suspended box needs no driven cofferdam and no tremie seal, but the piles must carry the box and the wet concrete before the cap is complete.
Prefer a precast concrete shell over steel where corrosion maintenance must be avoided and a yard can cast it; steel is lighter to lift and easier to adapt to as-built pile positions.
Plant, pace and money
PlantYard, tugs, strand jacks or ballast systems, survey for setting.
ProductivityOne box every few weeks from a yard; setting in one or two tidal windows.
CostUSD 1-4 million per box, offset by faster caps.
Risks and controls
What goes wrong
Towing and setting in weather windows; seal failure at pile penetrations.
Quality assurance
Leak test after seating, level and position survey, grout collar inspection.
Origins
Suspended steel boxes and precast concrete cap shells developed with the long sea crossings of the 1990s and 2000s, particularly in China (Donghai Bridge 2005, Sutong 2008), replacing sheet-pile cofferdams where water was deep and the cap could stay above the bed.
Examples
Steel hanging boxes and precast cap shells are standard on Chinese sea and estuary crossings (Donghai, Sutong) and are used on US river bridges where sheets cannot be driven (Sellwood, Sikorsky); the game's high pile cap uses this rate.
Case studies
Sutong Yangtze River Bridge (pylon foundations)China · 2008Each pylon stands on 131 bored piles up to 2.8 m in diameter and over 110 m long under a 114 x 48 m cap, cast inside steel boxes with 2 m thick concrete-filled walls; one box of about 5,000 t was lowered in a single piece and also serves as ship-impact protection.
Donghai BridgeChina · 2005On the 20 km deep-sea section the pile caps were precast concrete boxes set on groups of raked steel pipe piles, with the pier shafts and girders also made in a casting yard.
Sellwood Bridge, Portland (Oregon)USA · 2013-2014River pier caps were built in a 'perched box' cofferdam assembled above water and jacked down (about 460 t) onto the pier shafts with eight cylinder jacks; no tremie concrete was needed.
Sikorsky BridgeUSA · 2003-2005A precast concrete 'bathtub' (305 mm slab and wall panels) was set inside a sheet-pile cofferdam that could not be dewatered, giving a dry box for the footing on 1.8 m drilled shafts.