Construction methods · Shallow foundations, cofferdams and dewatering

Tremie concrete seal

A mass of concrete placed underwater through a tremie pipe on the base of a cofferdam, thick enough that its weight plus friction on the sheet piles resists the uplift when the cofferdam is pumped dry. It converts a wet hole into a dry working floor.

Also called: underwater concrete plug, cofferdam seal, tremie plug

Tremie concrete seal — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Design the seal for uplift (its weight plus bond to piles and sheets), for bending between piles, and for the construction stage; specify a cohesive, highly workable mix with retarder and, for long flow distances, an anti-washout admixture.
  2. Excavate to grade and clean the base and the pile and sheet surfaces by airlift, jetting or divers with brushes, since bond to the piles carries much of the uplift; sound the base on a grid to confirm level.
  3. Set tremie pipes of 200-300 mm with watertight flanged joints on a gantry at 3-6 m spacing, marked for depth, with hoppers above water.
  4. Start each pipe with its tip on the base and a plug or go-devil separating concrete from water; lift slightly to release the charge and keep the tip at least 1-1.5 m inside fresh concrete from then on.
  5. Pour continuously, raising the surface evenly and moving pipes in a planned sequence; sound the surface regularly. If a pipe loses its seal, withdraw, re-plug and restart; never let concrete fall through water.
  6. Leave the seal to gain strength for 3-7 days, then dewater in stages, watching for leaks at pile and sheet interfaces and repairing them before going lower.
  7. Remove laitance and high spots down to sound concrete before casting the footing; core the seal where quality is in doubt.

Key numbers

Where it fits

  • Sheet-pile and double-wall cofferdams in sand and gravel where the base would boil; pile caps in water built inside cofferdams.

Where it does not

  • Thin seals in deep water: the seal thickness is often 1-3 m and can exceed the footing itself.

Choosing it

Plant, pace and money

PlantTremie pipes and hoppers, concrete pump or crane and skips, divers.
Productivity300-1,000 m3 per day per pour.
CostUSD 200-350 per m3, plus a lot of concrete you never see.

Risks and controls

What goes wrong

  • Pipe tip lifting out of the concrete and washing the mix; cold joints from an interrupted pour; seal cracking and leaking under uplift.

Quality assurance

Continuous pour log, soundings during placement, diver inspection of the surface, cube tests on the mix.

Origins

Placing concrete underwater through a tremie (French for hopper) dates from the 19th century; anti-washout admixtures, in use since the 1970s and 1980s, made wide, thin and self-levelling underwater placements reliable.

Examples

Standard under river pier cofferdams worldwide; also used to plug pile caps of the game's water piers when the cap is low.

Case studies

Sikorsky BridgeUSA · 2003A tremie seal was considered and rejected because it would have stood above the mudline in the navigation channel and needed later removal; a precast 'bathtub' inside the cofferdam replaced it.
Kabinakagami River Bridge replacementCanada · 2008The geotechnical report recommended a tremie plug or mud mat at the base of the abutment cofferdam; none was placed and the soft base heaved.
Akashi Kaikyo Bridge (main tower foundations)Japan · 1998Steel caissons about 80 m in diameter were set on the excavated seabed and filled with anti-washout underwater concrete in the strong tidal currents of the strait.

Related methods

Further reading

ACI 304R · FHWA guidance on underwater concrete · Gerwick, Construction of Marine and Offshore Structures · Caltrans Trenching and Shoring Manual (cofferdams and seal courses)