Construction methods · Site investigation and testing
Bi-directional (Osterberg cell) load test
A hydraulic jack cast into the pile pushes the upper part of the shaft up against the lower part and base. No kentledge, no reaction piles, and loads far beyond what a surface test can reach: the standard proof for large bored piles and barrettes.
Also called: O-cell test, bi-directional static load test
Concept diagram (TheBridgeEng)
How it is done
Choose the cell level from the predicted resistance profile so that the shaft resistance above the cell balances the shaft and base resistance below it; use two levels to test base and shaft zones separately.
Weld the cell assembly between bearing plates into the reinforcement cage; fit hydraulic lines, displacement transducers, telltales and strain gauges at layer boundaries, and pressure-test the lines before lowering.
Lift and lower the cage with care, as the cell plane is a weak section in handling, and concrete by tremie so that concrete fills around and below the plates.
When the concrete has gained strength, pressurise the cell in 15–20 increments, holding each for a few minutes and recording cell expansion and upward and downward movement.
In multi-level tests, load each segment in turn with the other cell left free, so that base and shaft sections are measured separately.
Construct the equivalent top-down curve by adding upward and downward resistances at equal movement, corrected for elastic shortening.
Grout the cell and the gap if the pile is to serve as a working pile; report unit shaft resistance per layer and the base response.
Key numbers
Equivalent top load is about twice the cell load in a balanced test, since the cell loads up and down at once.
Several cells grouped at one level reach total test loads of 50–300 MN on large shafts.
Record loadsabout 280 MN on an Incheon Bridge shaft in 2005; more than 300 MN reported since on single piles and barrettes.
Economic thresholdusually cheaper than a kentledge or reaction-pile test above about 20 MN.
Test durationone to two days after curing, with a sacrificial cell.
Where it fits
Bored piles and barrettes above about 1.5 m diameter, pylon foundations, marine piles where reaction systems are impractical.
Tests to 50-300 MN.
Where it does not
Driven piles (the cell cannot be cast in); small piles where a conventional test is cheaper.
Choosing it
Choose a bi-directional test over a top-down test when the load needed is beyond what kentledge or reaction piles can practically supply (roughly 20–30 MN), or when the pile is over water.
Prefer a top-down test when the behaviour of the pile head matters directly (lateral load, group interaction, downdrag) or the pile is small.
Use multi-level cells when base and shaft must be separated, or when the expected resistances above and below one level are far from balanced.
Accept that the test pile is usually sacrificial unless the cell is grouted and the design allows its use as a working pile.
Plant, pace and money
PlantThe cell, hydraulic pump, data logger; no reaction frame.
ProductivityOne to two days of testing after curing; the cell is sacrificial.
CostUSD 100,000-400,000 per test depending on cell size; cheaper than kentledge above about 20 MN.
Risks and controls
What goes wrong
Cell placed at the wrong level gives an unbalanced test that stops early.
The tested pile is usually not used as a production pile without grouting the cell.
Quality assurance
Pre-test cage inspection, calibrated cells, strain gauge levels matched to the soil profile.
Origins
Developed by Jorj Osterberg of Northwestern University, who patented the cell in 1987; its first major use was on a large drilled shaft for a bridge near Daytona, Florida, and ASTM issued D8169 for bi-directional static testing in 2018.
Examples
Used on many long-span bridge pylon foundations since the 1990s, including sea crossings in Asia and the Gulf; multi-level cells are now common on piles and barrettes above about 2 m diameter.
Case studies
Incheon BridgeSouth Korea · 2005A bi-directional test on a 3.05 m diameter shaft about 67 m long reached about 280 MN, a record at the time.
Golden Ears BridgeCanada · 2006A two-level test on a 2.5 m bored pile about 74 m long in deltaic sands and clays showed combined resistance above 62 MN, but toe resistance only 37 % of the expected value, which was attributed to debris on the base.
Bridge near Daytona, FloridaUSA · late 1980sFirst major use of the O-cell, on a large drilled shaft, by Schmertmann and Crapps.