Construction methods · Piers, pylons and abutments

Precast segmental piers and caps

Piers and caps cast in a yard as segments or complete units, stacked on site in hours and connected with grouted couplers, post-tensioning or grouted sleeves. Removes formwork, curing and scaffold from the site: the substructure half of accelerated bridge construction.

How bridges get built · Piers, pylons and abutments · Precast segmental piers and caps

Also called: prefabricated substructure, precast column segments, ABC substructure

How it is done

  1. Choose the connections first (match-cast epoxy joints with vertical post-tensioning, grouted ducts, grout pockets or grouted sleeve couplers) and build a full-size mock-up of the critical one.
  2. Cast the column segments and caps in the yard to tight tolerances, match-casting segments that will be epoxied and fixing ducts or sleeves with templates.
  3. Prepare the footing: set the projecting bars, tendon anchorages or ducts with a template, and set levelling shims or friction collars at the bearing level.
  4. Set the first segment or the column on shims and grout the bed with high-strength non-shrink grout.
  5. Stack the segments with epoxy and temporary bars, surveying plumb and twist at every joint.
  6. Lower the cap onto the column with the projecting bars entering the ducts or pockets; support it on shims or collars and grout the connection.
  7. Stress and grout the vertical tendons where used, seal the anchorages and test the grout.
  8. Release the temporary supports after the grout reaches strength, then survey the bearing seats.

Key numbers

Where it fits

  • Long viaducts with repetitive piers, urban and railway sites with short closures, marine viaducts where site work is expensive, seismic regions with proven connection details.

Where it does not

  • Piers that all differ, very tall piers, sites without a yard or a heavy crane.

Choosing it

Plant, pace and money

PlantPrecast yard, transport, 200-500 t crane, stressing and grouting plant.
ProductivityA pier in one to three days on site versus two to three weeks cast in place.
Cost10-25 % more per pier than cast-in-place; recovered in time and in reduced site risk.

Risks and controls

What goes wrong

  • Joint grout quality, duct blockages, tolerance stacking, connection performance in earthquakes.

Quality assurance

Match-cast records, grout tests, tendon stressing, connection mock-ups for seismic details.

Origins

Precast segmental piers erected from the deck were used on the Linn Cove Viaduct (completed 1983), and Texas DOT developed precast bent caps with grout-pocket and grouted-duct connections in the 1990s; FHWA's accelerated bridge construction programmes since the 2000s spread prefabricated substructures, with seismic connections still being developed and tested.

Examples

Hong Kong-Zhuhai-Macau approaches, Florida and Texas ABC projects, Korean coastal viaducts.

Case studies

Linn Cove Viaduct, Blue Ridge ParkwayUSA · 1983Hollow precast box piers, vertically post-tensioned and erected from the deck above; only the footings on micropiles were cast in place.
Red Fish Bay bridgesUSA · mid-1990sEarly Texas precast bent caps on precast trestle piles, connected through grout pockets with dowels grouted into sleeves in the piles.
Lake Belton Bridge (SH 36), near TempleUSA · 2000s62 identical precast bent caps of about 12 m and 68 t, connected by grouted ducts and set on 50 mm shims about 15 m above the lake.
Confederation BridgeCanada · 1997Pier bases, shafts and girders were precast on shore and set by a heavy-lift floating crane, keeping almost all concrete work off the Northumberland Strait.

In the bridge game

What Bridge Master applies when you pick it

Deck types: any. Spans 20-60 m, up to 100 m.

  • +30: Precast piers assembled in days.
  • -40: A substructure option, not a deck erection method: the deck still needs one of the other methods.

Try it in the game →

Related methods

Further reading

FHWA ABC Manual · PCI Bridge Design Manual Chapter 16 · AASHTO Guide Specifications for ABC · NCHRP Report 681, Development of a Precast Bent Cap System for Seismic Regions · FHWA, Connection Details for Prefabricated Bridge Elements and Systems