Construction methods · Cable-supported and arch bridges

Network tied arch construction

A network tied arch (inclined hangers crossing twice or more) is light enough to be built whole on falsework or on the bank and moved in, because the arch and tie are slender. The hangers are installed and tensioned in a strict sequence so that none goes slack during the deck pour.

How bridges get built · Cable-supported and arch bridges · Network tied arch construction

Also called: network arch erection, crossing hanger arch

Network tied arch construction — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Fix the erection and hanger sequence at design stage: hanger forces are sensitive to the order of deck casting, and a changed sequence can slacken or overload hangers.
  2. Build the tie: assemble the steel tie or cast the concrete tie on temporary supports, falsework or an assembly yard.
  3. Erect the arch ribs on temporary towers standing on the tie or the ground, and complete the wind bracing between the ribs.
  4. Install the inclined hangers (rods or strands) in the planned order and pretension them so each carries a small force before the main loads arrive.
  5. Cast the deck slab in the analysed sequence (often in strips from midspan outward or in alternating panels), monitoring hanger forces and arch geometry and adjusting hanger lengths where the sequence requires.
  6. Remove the temporary supports, or move the completed span by float-in, slide or SPMT and set it on its bearings.
  7. Measure final hanger forces (vibration or lift-off) and arch geometry as the inspection baseline.

Key numbers

Where it fits

  • Single spans of 80-260 m over rivers, canals and railways; replacement spans that must go in during a short closure.

Where it does not

  • Sites where the assembly area does not exist; designs without a hanger sequence analysis.

Choosing it

Plant, pace and money

PlantFalsework or assembly yard, cranes, hanger stressing equipment, movers.
ProductivityAssembly in months; installation in a day.
CostSteel USD 5,000-8,000 per tonne erected.

Risks and controls

What goes wrong

  • Slack hangers during deck casting, arch buckling before the deck stiffens the system.

Quality assurance

Hanger force records at each stage, arch geometry survey.

Origins

Per Tveit developed the network arch in Norway; the first two, at Steinkjer and Bolstadstraumen, were completed in 1963–64, and the type spread to Germany, the US and elsewhere from the 2000s.

Examples

Brandanger (Norway), Providence River, Blennerhassett, many Norwegian and German road bridges; the game's network tied arch type.

Case studies

Steinkjer BridgeNorway · 1963One of Per Tveit's first two network arches (with Bolstadstraumen, 1964).
Blennerhassett Island BridgeUSA · 2008268 m network tied arch over the Ohio River, assembled on shore and floated into position on barges.
Brandanger BridgeNorway · 2010220 m network arch across a fjord, built to Tveit's principles.

Related methods

Further reading

Tveit, network arch publications · NCHRP guidance on tied arches