Construction methods · Cable-supported and arch bridges

Cable crane (cableway) erection

A carrying cable strung between towers on each side of a gorge with a trolley that lifts arch segments or truss members from the valley floor or the banks and delivers them anywhere along the span. The classic plant of arch bridges in mountains and the standard in Chinese arch construction.

How bridges get built · Cable-supported and arch bridges · Cable crane (cableway) erection

Also called: cableway crane, aerial cableway, cable crane for arches

Cable crane (cableway) erection — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Design the cableway for the heaviest segment with rigging and dynamic effects: span between towers, sag, number of track cables, tower height and backstay anchorages.
  2. Build the towers (on or behind the abutments, often 50–150 m tall) and their anchorages; string the track cables, hauling and hoisting ropes and the trolleys.
  3. Load-test the system (static and dynamic overload tests, commonly 1.1–1.25 times the working load) and set wind and operating limits.
  4. Lift segments from the staging area or a barge, traverse to position and lower them onto the cantilever tip, the falsework or the arch skeleton, coordinating each placement with the tie-back stay installation.
  5. Monitor tower tilt, anchorage loads and rope wear, and inspect ropes and sheaves on a fixed schedule.
  6. After arch closure, use the cableway for spandrel columns, cross beams and deck elements, then dismantle the ropes and towers.

Key numbers

Where it fits

  • Steel and concrete arch segments of 50-300 t over gorges 200-600 m wide; truss erection; sites with no road access to the span.

Where it does not

  • Flat sites where a crane or gantry is cheaper; loads beyond the cableway capacity.

Choosing it

Plant, pace and money

PlantCable crane system 100-400 t, towers, winches, anchorages.
ProductivitySeveral lifts per day.
CostUSD 3-15 million for the system; a large item in the arch budget.

Risks and controls

What goes wrong

  • Tower or anchorage failure, rope wear, load swing in wind.

Quality assurance

Rope inspection, load tests, wind limits.

Origins

Cableways were used to build dams and mountain arches from the late 19th century; New River Gorge (1977) used them for a 518 m steel arch, and in China cable cranes combined with tie-back stays became the standard way of building CFST and stiff-skeleton arches from the 1990s.

Examples

New River Gorge (518 m, 1977), Hoover Dam bypass (2010), and Chinese CFST arches such as Wushan (460 m, 2005) and Pingnan Third (575 m, 2020).

Case studies

New River Gorge BridgeUSA · 1977518 m steel arch cantilevered from both rims with tie-backs, the steel delivered by cableways spanning the gorge.
Mike O'Callaghan–Pat Tillman Memorial Bridge (Hoover Dam bypass)USA · 2010High-line cable cranes across Black Canyon served the 323 m arch; one system collapsed in high winds in 2006, delaying the project by about two years.
Pingnan Third BridgeChina · 2020575 m CFST arch; prefabricated sections of up to about 215 t, shipped by water, were placed by a large cable crane on two tall truss towers, with the half-arches anchored back to the towers.

In the bridge game

What Bridge Master applies when you pick it

Deck types: Concrete arch, Steel arch, Steel truss, Precast segmental box. Spans 150-450 m, up to 600 m.

  • +30: Very deep gorge: cableway.
  • -40: Only for gorges.

Try it in the game →

Related methods

Further reading

Chen and Duan, Bridge Engineering Handbook · Chinese arch bridge construction papers