Construction methods · Caissons and marine foundations

Steel pipe sheet pile (SPSP) well foundation

Interlocking steel pipe piles are driven in a ring; the interlocks are grouted so the ring works as a rigid well, and a top slab ties it together. The ring is first the cofferdam and then the permanent foundation: a Japanese method that cut river and coastal pier construction time dramatically.

How bridges get built · Caissons and marine foundations · Steel pipe sheet pile (SPSP) well foundation

Also called: SPSP foundation, steel pipe sheet pile cofferdam foundation, koukan yaita

Steel pipe sheet pile (SPSP) well foundation — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Set a guide frame or template on temporary piles and pitch the first steel pipe sheet piles (typically 800–1,500 mm) with welded joint pipes that interlock with the next pile.
  2. Drive the ring with vibratory and hydraulic hammers into the bearing layer, closing the ring carefully and checking verticality and joint engagement as each pile goes down.
  3. Flush the joint pipes and fill them with mortar so that the ring acts as a closed well, transferring shear between piles.
  4. Use the upper part of the ring as a cofferdam: excavate inside, place a tremie concrete seal, install walings and struts, and dewater.
  5. Cast the top slab rigidly connecting all pile heads, with shear connectors on the inside faces of the piles.
  6. Build the pier on the slab, then cut off the temporary upper part of the ring below the bed or low water, or leave it as protection.

Key numbers

Where it fits

  • River and coastal piers in 5-20 m of water with sandy or clayey beds, high lateral loads (ships, earthquakes), sites where a separate cofferdam would double the time.

Where it does not

  • Rock at shallow depth (piles cannot embed), very small piers (uneconomic).

Choosing it

Plant, pace and money

PlantBarge with template, vibro and hydraulic hammers, interlock grouting plant.
ProductivityA ring of 60-100 piles in one to two months; then the slab and pier.
CostUSD 3-12 million per pier; cheaper than caisson plus cofferdam where it fits.

Risks and controls

What goes wrong

  • Interlock leakage and grout quality, driving refusal on obstructions, corrosion.

Quality assurance

Interlock grout tests, ring verticality, dewatering watch.

Origins

Developed in Japan from 1961 from a German box-pile wall concept of the 1930s, the steel pipe sheet pile foundation was first used for a blast-furnace foundation in 1967 and for a bridge at the Ishikari Kakō Bridge in 1969; the Japan Road Association now publishes a dedicated design and construction handbook.

Examples

Japanese river and coastal bridges since 1969; the Nhat Tan and Lach Huyen bridges in Vietnam; steel pipe sheet piles with mechanical joints were also used in the Haneda Airport D Runway works.

Case studies

Ishikari Kakō Bridge, HokkaidoJapan · 1969 (foundation)First bridge use of the steel pipe sheet pile foundation, after eight years of development and a first industrial use in 1967.
Nhat Tan Bridge, HanoiVietnam · 2015Five-pylon cable-stayed bridge with 4 × 300 m main spans; its SPSP well foundations, the first in Vietnam, served as cofferdam and permanent structure.
Lach Huyen Bridge, HaiphongVietnam · 2017Sea crossing to Lach Huyen port founded on steel pipe sheet pile foundations, a further Japanese-assisted application in Vietnam.

Related methods

Further reading

Japanese Steel Pipe Sheet Pile Foundation design guidelines · Japan Road Association specifications · Japan Road Association, Handbook for Design and Construction of Steel Pipe Sheet Pile Foundations