Construction methods · Caissons and marine foundations
Steel pipe sheet pile (SPSP) well foundation
Interlocking steel pipe piles are driven in a ring; the interlocks are grouted so the ring works as a rigid well, and a top slab ties it together. The ring is first the cofferdam and then the permanent foundation: a Japanese method that cut river and coastal pier construction time dramatically.
Set a guide frame or template on temporary piles and pitch the first steel pipe sheet piles (typically 800–1,500 mm) with welded joint pipes that interlock with the next pile.
Drive the ring with vibratory and hydraulic hammers into the bearing layer, closing the ring carefully and checking verticality and joint engagement as each pile goes down.
Flush the joint pipes and fill them with mortar so that the ring acts as a closed well, transferring shear between piles.
Use the upper part of the ring as a cofferdam: excavate inside, place a tremie concrete seal, install walings and struts, and dewater.
Cast the top slab rigidly connecting all pile heads, with shear connectors on the inside faces of the piles.
Build the pier on the slab, then cut off the temporary upper part of the ring below the bed or low water, or leave it as protection.
Key numbers
Pipe diameter800–1,500 mm
Ring sizeabout 10–30 m across, circular, oval or rectangular
Water depthabout 5–20 m
Piles per ringabout 40–100 or more
Programmea ring of 60–100 piles in one to two months, then slab and pier
Where it fits
River and coastal piers in 5-20 m of water with sandy or clayey beds, high lateral loads (ships, earthquakes), sites where a separate cofferdam would double the time.
Where it does not
Rock at shallow depth (piles cannot embed), very small piers (uneconomic).
Choosing it
Choose it over a sheet-pile cofferdam plus a pile group in 5–20 m of water: one set of steel serves as cofferdam and foundation, saving months on river and estuary piers.
Choose it where lateral loads (earthquake, ship, ice) are high and soft upper soils would make an ordinary pile group flexible.
Prefer an open caisson or bored piles where rock or boulders lie close below the bed; the pipes must be driven well into the bearing layer.
Prefer bored piles in a cofferdam for small piers or where impact driving is not permitted for noise reasons.
Plant, pace and money
PlantBarge with template, vibro and hydraulic hammers, interlock grouting plant.
ProductivityA ring of 60-100 piles in one to two months; then the slab and pier.
CostUSD 3-12 million per pier; cheaper than caisson plus cofferdam where it fits.
Risks and controls
What goes wrong
Interlock leakage and grout quality, driving refusal on obstructions, corrosion.
Quality assurance
Interlock grout tests, ring verticality, dewatering watch.
Origins
Developed in Japan from 1961 from a German box-pile wall concept of the 1930s, the steel pipe sheet pile foundation was first used for a blast-furnace foundation in 1967 and for a bridge at the Ishikari Kakō Bridge in 1969; the Japan Road Association now publishes a dedicated design and construction handbook.
Examples
Japanese river and coastal bridges since 1969; the Nhat Tan and Lach Huyen bridges in Vietnam; steel pipe sheet piles with mechanical joints were also used in the Haneda Airport D Runway works.
Case studies
Ishikari Kakō Bridge, HokkaidoJapan · 1969 (foundation)First bridge use of the steel pipe sheet pile foundation, after eight years of development and a first industrial use in 1967.
Nhat Tan Bridge, HanoiVietnam · 2015Five-pylon cable-stayed bridge with 4 × 300 m main spans; its SPSP well foundations, the first in Vietnam, served as cofferdam and permanent structure.
Lach Huyen Bridge, HaiphongVietnam · 2017Sea crossing to Lach Huyen port founded on steel pipe sheet pile foundations, a further Japanese-assisted application in Vietnam.
Japanese Steel Pipe Sheet Pile Foundation design guidelines · Japan Road Association specifications · Japan Road Association, Handbook for Design and Construction of Steel Pipe Sheet Pile Foundations