Construction methods · Piers, pylons and abutments

Climbing and jump formwork

Formwork that lifts itself on the pier it has just cast, anchored into the previous lift, with working platforms attached. Crane-climbed systems move with a crane; self-climbing systems use hydraulic rams and free the crane entirely. The method for tall piers and every concrete pylon.

How bridges get built · Piers, pylons and abutments · Climbing and jump formwork

Also called: jump form, self-climbing formwork, crane-climbing formwork

Climbing and jump formwork — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Cast the first one or two lifts conventionally and set the climbing anchors (cast-in cones or bolts) in the last lift at the bracket positions on the climbing drawings.
  2. Mount the brackets or rails on the anchors and build the platforms: reinforcement deck above, main working deck at form level, and a trailing finishing platform below for anchor recovery and patching.
  3. Cycle: fix reinforcement and embeds (prefabricated cages where possible), set the next anchors, close and plumb the forms, pour the 4–5 m lift and strip.
  4. Climb only when the concrete at the new anchors has reached the supplier's minimum strength: crane-climbing units are lifted as complete units, self-climbing units jack their rails and brackets up on hydraulic cylinders without the crane.
  5. Adjust the panels for taper, wall-thickness changes and inclination; inclined pylon legs need temporary struts or ties until the cross beam is built.
  6. Survey every lift for position, verticality and twist at a fixed time of day (early morning) with temperature correction, and correct drift gradually over several lifts.
  7. Observe hold points before each climb (anchor record, platforms cleared of stored material, wind below the climbing limit); at the top, dismantle by crane and make good the anchor holes.

Key numbers

Where it fits

  • Piers over 25 m, valley viaducts, concrete pylons of 60-300 m, inclined pylon legs (with tie-backs during construction).

Where it does not

  • Short piers, where the setup costs more than it saves.

Choosing it

Plant, pace and money

PlantClimbing system (Doka, Peri or similar), tower crane or self-climbing hydraulics, concrete pump with placing boom.
ProductivityOne 4-5 m lift per 4-7 days per leg; a 150 m pylon in 8-12 months.
CostUSD 600-1,200 per m3 of pylon concrete including the system.

Risks and controls

What goes wrong

  • Anchor failure during climbing, wind on platforms, geometry drift accumulating over the height, cable anchorage zones with congested reinforcement.

Quality assurance

Survey of every lift (verticality within height/1,000 or better), anchor cone tests, reinforcement cover checks, temperature control in thick sections.

Origins

Climbing forms grew out of shaft, chimney and dam construction; crane-climbed bracket systems were common on tall bridge piers by the 1960s and 1970s, and hydraulic self-climbing systems became normal on tall piers and pylons from the 1990s.

Examples

Millau (245 m piers), Sutong and Russky pylons, Incheon Bridge pylons; the game's pylon duration is based on lift cycles.

Case studies

Millau ViaductFrance · 2004Concrete piers up to 245 m (pier P2) climbed in lifts of about 4 m; each pier splits into two thinner shafts for its top 90 m.
Russky Bridge, VladivostokRussia · 2012A-shaped concrete pylons 320.9 m high, climbed lift by lift in a harsh winter climate for a 1,104 m cable-stayed span.
Willow Island cooling towerUSA · 1978Not a bridge, but the defining climbing-form accident: 51 workers died when the climbing scaffold fell because the concrete holding its anchors was too young.

Related methods

Further reading

fib Bulletin 48 (formwork) · manufacturer engineering guides