Construction methods · Ground improvement

Piled embankment with load-transfer platform

A grid of piles or columns with small caps, a geogrid-reinforced granular platform on top, and the embankment above. The fill arches onto the caps and the soft clay is bypassed: no waiting for consolidation, no long-term settlement at the abutment.

How bridges get built · Ground improvement · Piled embankment with load-transfer platform

Also called: basal reinforced piled embankment, geosynthetic-reinforced pile-supported embankment, GRPS

Piled embankment with load-transfer platform — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Design the pile grid and caps for load transfer by arching (BS 8006-1, EBGEO or CUR 226), the geosynthetic for the vertical load between caps and for lateral sliding at the edges, and check the differential settlement at the surface.
  2. Install piles on a 1.5–3.0 m grid: driven precast or timber, CFA, vibro concrete columns, or DCM and stone columns for lighter cases; cut them to level.
  3. Cast pile caps of about 0.6–1.5 m square, or a continuous slab in transition zones.
  4. Place a thin granular layer and the first geogrid just above the caps, laid flat with design overlaps and the strong direction across the embankment.
  5. Build the 0.5–1.0 m load-transfer platform of compacted granular fill with one to three geogrid layers.
  6. Build the embankment; arching needs a fill height of at least about 0.7 times the clear spacing between caps, and below that the surface shows differential settlement.
  7. Monitor settlement of the caps and of the ground between them, and the strain in the geogrid.

Key numbers

Where it fits

  • Approaches on very soft or organic soil, where the programme is short, or where the approach must not settle against a fixed abutment.

Where it does not

  • Thin soft layers where PVDs are far cheaper.

Choosing it

Plant, pace and money

PlantPiling rig, earthmoving, geogrid laying crew.
ProductivityPiling dominates: 40-80 piles per rig per day.
CostUSD 150-400 per m2 of embankment footprint, two to four times a PVD scheme, but no waiting.

Risks and controls

What goes wrong

  • Punching of caps through the platform if the geogrid is under-designed; lateral spreading at the embankment toe.

Quality assurance

Pile records, geogrid overlap and tension checks, settlement plates on caps and between them.

Origins

Piled embankments with timber or concrete piles and caps were used in Scandinavia and the Netherlands from the 1960s and 1970s; geosynthetic load-transfer platforms followed in the 1980s, with design methods from Hewlett and Randolph (1988), BS 8006 (1995), EBGEO (2010) and CUR 226 (2010).

Examples

Dutch and Scandinavian railways, Korean high-speed rail approaches, Bangkok expressway ramps.

Case studies

Beijing–Shanghai High-Speed RailwayChina · 2011Pile-supported embankments on cement-fly ash-gravel and similar piles were used over long soft-ground sections to meet very strict post-construction settlement limits.
Channel Tunnel Rail Link (High Speed 1)United Kingdom · 2007Piled embankments and piled slabs carried the line across the soft alluvium of the Thames marshes.

Related methods

Further reading

BS 8006-1 · CUR 226 (Dutch design guideline) · EBGEO, Recommendations for Design and Analysis of Earth Structures using Geosynthetic Reinforcements (German Geotechnical Society) · Hewlett and Randolph (1988) Analysis of piled embankments