Construction methods · Piers, pylons and abutments

MSE (reinforced soil) abutments

The approach fill itself is turned into a wall with layers of steel strips or geogrid behind precast facing panels, and the deck sits on a small seat on top or on piles through the fill. Cheaper and faster than a concrete wall, tolerant of settlement, and the standard in the game and in most highway practice for fills up to about 12-15 m.

How bridges get built · Piers, pylons and abutments · MSE (reinforced soil) abutments

Also called: mechanically stabilised earth abutment, reinforced earth, GRS abutment

How it is done

  1. Check foundation bearing, global stability and settlement; treat or replace soft ground, then cast an unreinforced levelling pad to line and level.
  2. Set the first row of facing panels with clamps and temporary bracing, battered back slightly to allow for outward movement during compaction.
  3. Place select granular fill in 200–300 mm lifts, compacting with heavy rollers away from the face and only light plate compactors within about 1 m of it; lay each layer of strips or geogrid flat and perpendicular to the face and connect it to the panels.
  4. Repeat row by row, checking face alignment and batter on every row and covering panel joints with filter fabric.
  5. For a true MSE abutment, cast the seat footing on the reinforced fill within the bearing limit and setback; for a mixed abutment, install the piles first and carry them through the fill in sleeves so the seat rests on the piles.
  6. Cast the coping, the barrier with its moment slab, the underdrain and surface drainage, and the approach slab.
  7. Monitor face movement and settlement, particularly where the wall sits on compressible ground or preloading was used.

Key numbers

Where it fits

  • Fills of 4-15 m on competent ground, highway interchanges, sites where formwork and cranes are scarce, seismic regions (ductile).

Where it does not

  • Soft foundation soils without treatment, aggressive or saline fill (corrosion of steel strips), scour-exposed river banks.

Choosing it

Plant, pace and money

PlantSmall crane or excavator for panels, compaction plant, no formwork.
Productivity1-2 m of wall height per day.
CostUSD 250-450 per m2 of face, roughly half of a concrete wall.

Risks and controls

What goes wrong

  • Fill of the wrong grading, corrosion of reinforcement in wet or saline fill, panel bulging from poor compaction, seat settlement on a true MSE abutment.

Quality assurance

Fill grading and electrochemical tests, compaction tests per layer, panel alignment survey.

Origins

Henri Vidal patented Reinforced Earth in France in 1963; the first US Reinforced Earth wall was built on California State Route 39 in 1972, and MSE abutments became common in highway practice from the 1980s.

Examples

Highway interchanges worldwide since the 1970s; Gulf highways use them almost exclusively.

Case studies

State Route 39, San Gabriel MountainsUSA · 1972The first Reinforced Earth wall in the United States, which opened the way for MSE walls and abutments on US highways.
Bowman Road Bridge, Defiance County, OhioUSA · 2005The first geosynthetic reinforced soil integrated bridge system (GRS-IBS): the short-span superstructure bears directly on the reinforced fill without piles.

Related methods

Further reading

FHWA GEC 11 (MSE walls) · AASHTO LRFD 11.10 · BS 8006 · FHWA GRS-IBS Interim Implementation Guide