Construction methods · Cast-in-place concrete decks

Falsework and temporary works engineering

Every cast-in-place method relies on a temporary structure that carries the wet concrete, the crew and the plant. Falsework has killed more construction workers than any permanent structure; the procedures that prevent it are as much a method as any formwork.

How bridges get built · Cast-in-place concrete decks · Falsework and temporary works engineering

Also called: temporary works design, falsework check, temporary works coordinator

Falsework and temporary works engineering — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Appoint a temporary works coordinator and keep a register of every temporary structure: falsework, formwork, cofferdams, travellers, gantries and trestles.
  2. Write a design brief for each item: loads (wet concrete, construction live load, wind, lateral load, pour rate and pump surge), ground information, interfaces, deflection limits and programme.
  3. Design it, or check the supplier's standard solution against the brief, and have it independently checked at the level its risk requires (BS 5975 check categories 0–3).
  4. Verify the foundations (bearing, drainage and protection), with plate load tests where the ground is doubtful.
  5. Inspect the erected structure against the drawings and issue a permit to load (hold point) before any concrete or plant goes on.
  6. Monitor during loading (tell-tales, settlement and deflection) against stop criteria agreed in advance.
  7. Issue a permit to strike only when the permanent structure can carry itself (cube or maturity results, stressing complete), and dismantle in the designed sequence.

Key numbers

Where it fits

  • Every project with formwork, falsework, cofferdams, travellers, gantries or trestles.

Where it does not

  • Treating the supplier's catalogue as a design; loading before the permit.

Choosing it

Plant, pace and money

PlantNone; it is procedure and engineering.
ProductivityAdds days of engineering, saves lives.
Cost1-3 % of temporary works cost.

Risks and controls

What goes wrong

  • The collapse of falsework, cofferdams and gantries: Willow Island (1978), Injaka (1998), several MSS collapses since 2000.

Quality assurance

Design and check certificates, permit-to-load records, striking release records.

Origins

Systematic temporary works control began in the UK after a run of falsework collapses, including the Loddon Bridge at Reading in 1972, led to the Bragg Committee report (1975), BS 5975 (1982) and the temporary works coordinator role; the FHWA Guide Design Specification for Bridge Temporary Works and ASCE 37 followed in the US.

Examples

BS 5975 in the UK codifies the whole procedure.

Case studies

Sandö Bridge, Ångerman RiverSweden · 1939The timber centering for the 264 m concrete arch collapsed during construction, killing 18 workers; the arch was rebuilt and opened in 1943.
Injaka Bridge, MpumalangaSouth Africa · 1998An incrementally launched deck collapsed during launching with 14 deaths; the inquiry made it a reference case for temporary works design checks and site control.

Related methods

Further reading

BS 5975 · ASCE 37 · Temporary Works Forum guidance · Final report of the Advisory Committee on Falsework (Bragg report, 1975) · BS EN 12812 Falsework · FHWA Guide Design Specification for Bridge Temporary Works