Construction methods · Cast-in-place concrete decks

Form travellers and traveller anchorage

The moving formwork of balanced cantilever construction: a steel frame anchored to the last segment carries the soffit, web and top forms for the next one, then rolls forward. Its anchorage is the most safety-critical bolt group on the site.

How bridges get built · Cast-in-place concrete decks · Form travellers and traveller anchorage

Also called: cantilever form traveller, traveller, CFT

How it is done

  1. Select the traveller: an overhead truss (simple, handles variable depth) or an underslung frame (keeps the deck top clear for stays and cranes); size it for the heaviest segment and keep its self-weight low to limit the unbalanced moment.
  2. Assemble the pair back to back on the pier table, fix the rails and anchor them with high-strength bars through the deck; load-test the traveller or monitor the first pour against predicted deflections.
  3. Advance: release the forms from the cast segment, lower the soffit, release the rear anchors and roll forward on the rails with hydraulic cylinders, symmetrically on both cantilevers.
  4. Re-anchor: install and stress the anchor bars to the specified force and record it (hold point before any load goes on).
  5. Set the forms to the casting curve (theoretical profile plus predicted deflections), confirm by survey, then fix reinforcement and ducts and pour.
  6. Compare the measured traveller deflection with the prediction after each pour and recalibrate the casting curve.
  7. At the end of the cantilever, use one traveller or a closure frame for the closure pour, then roll the travellers back to the pier and lift them off or lower them to a barge.

Key numbers

Where it fits

  • All cast-in-place balanced cantilever decks, extradosed bridges, cable-stayed concrete decks cast on travellers with stays supporting the tip.

Where it does not

  • Unchecked anchorages; overloading the traveller with stored materials.

Choosing it

Plant, pace and money

PlantTraveller pair per pier, hydraulics, rails and anchor bars.
ProductivityThe traveller cycle of 5-9 days sets the pace of the cantilever.
CostUSD 0.5-1.5 million per pair.

Risks and controls

What goes wrong

  • Anchorage failure and traveller drop, wind, rail misalignment during rolling.

Quality assurance

Load test, anchor bar tension checks every cycle, wind limits for rolling.

Origins

Developed by Dyckerhoff & Widmann under Ulrich Finsterwalder for the Lahn bridge at Balduinstein (1950–51), together with the high-strength threaded bars used both for prestressing and for anchoring the traveller.

Examples

Every balanced cantilever in the game's construction animation.

Case studies

Lahn Bridge, BalduinsteinGermany · 1951The first prestressed concrete bridge built by balanced cantilever with form travellers and threaded bars.
Raftsundet BridgeNorway · 1998298 m main span cast segment by segment from form travellers; with Stolma, the longest concrete cantilever spans.

Related methods

Further reading

Rosignoli, Bridge Construction Equipment · Mathivat, The Cantilever Construction of Prestressed Concrete Bridges