Construction methods · Precast concrete decks

Deck slabs on girders: cast-in-place, precast panels and stay-in-place forms

The slab that turns a row of girders into a bridge. Cast in place on removable or stay-in-place forms, or laid as partial-depth precast panels with a topping, or as full-depth precast panels post-tensioned together for speed. The choice decides the site time after the girders are up.

How bridges get built · Precast concrete decks · Deck slabs on girders: cast-in-place, precast panels and stay-in-place forms

Also called: composite deck slab, precast deck panels, stay-in-place formwork, full-depth precast deck

Deck slabs on girders: cast-in-place, precast panels and stay-in-place forms — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Survey the girder tops and set the haunch (build-up) over each girder to the deck profile, allowing for the remaining camber and the deflection under the slab weight.
  2. Install the forms: overhang brackets on the exterior girders and, between girders, removable forms, steel stay-in-place forms or partial-depth precast panels on bedding strips.
  3. Fix the bottom and top mats on chairs, check cover and shear connectors, and set the screed rails for the finishing machine.
  4. Pour in the planned sequence (positive moment regions first and regions over the piers last on continuous spans), using a finishing machine and a retarder for long pours.
  5. Wet-cure for about 7 days, starting fog sprays or evaporation control as soon as finishing allows.
  6. For full-depth precast panels, set the panels on levelling devices, then make the joints and fill pockets and haunches (see the full-depth panel method).
  7. Inspect cover and cracking at 28 days and seal cracks before waterproofing or surfacing.

Key numbers

Where it fits

  • All girder bridges; full-depth panels for accelerated construction and deck replacement.

Where it does not

  • Cast-in-place in freezing or very hot weather without protection; full-depth panels on girders with uncontrolled camber.

Choosing it

Plant, pace and money

PlantFormwork, finishing machine, curing, cranes for panels.
ProductivityCast-in-place 2-3 weeks per span; full-depth panels a few days.
CostCast-in-place USD 150-250 per m2; full-depth precast USD 300-450 per m2.

Risks and controls

What goes wrong

  • Early cracking from shrinkage and restraint, low cover over the top mat, panel seating gaps.

Quality assurance

Cover surveys, curing records, panel haunch grouting, crack mapping at 28 days.

Origins

Composite cast-in-place slabs on girders became standard once welded shear studs were adopted in the 1950s; stay-in-place steel forms and partial-depth precast panels spread in the US from the 1960s and 1970s to cut formwork labour, and full-depth panels grew with deck replacement and accelerated construction programmes.

Examples

Full-depth panels are standard for US deck replacements and Korean ABC.

Case studies

Woodrow Wilson Bridge (original), Washington DC areaUSA · 1983The deck was replaced with full-depth precast panels, an early large-scale use of panels for redecking a busy crossing.

Related methods

Further reading

PCI Full-Depth Deck Panel Guidelines · FHWA ABC Manual · NCHRP Report 380, Transverse Cracking in Newly Constructed Bridge Decks · ACI 345R Guide for Concrete Highway Bridge Deck Construction