Construction methods · Heavy lift, moving and accelerated construction

Bridge jacking and lifting

Lifting an existing or new deck on hydraulic jacks: to replace bearings, to raise a bridge for clearance, to correct settlement, or to lift a launched deck onto its bearings. Millimetres matter, and every jack must move together.

Also called: deck jacking, bridge raising, bearing jacking, synchronised lifting

How it is done

  1. Survey the structure and its current support reactions, by calculation and, where possible, by trial jacking with load cells; assess the deck and substructure for the temporary support condition at the jacking points.
  2. Design jacking points on the pier cap beside the bearings, on temporary brackets or frames founded on the pier or footing, or on temporary towers; add stiffeners or strengthening at the deck jacking positions.
  3. Install jacks with load cells and mechanical locking collars (or packing that follows the lift), connected to a synchronised, computer-controlled pump with displacement transducers at every point.
  4. Lift in small increments, often 1–5 mm per step at the start, checking load and displacement at each point against limits on differential movement; follow the lift with locking collars or packing.
  5. Hold the structure on mechanical locks or packing, never on hydraulic pressure alone, while the work is done (bearing replacement, plinth raising, settlement correction).
  6. Lower onto the new bearings or raised supports in the reverse sequence and confirm reactions after load transfer.
  7. Re-survey levels, inspect for cracking, and reset joints and approach levels.

Key numbers

Where it fits

  • Bearing replacement, clearance increases, ILM and slide landing, settlement correction.

Where it does not

  • Jacking without locks (hydraulic failure drops the deck); jacking a continuous deck at one pier without checking the others.

Choosing it

Plant, pace and money

PlantHydraulic jacks (50-1,000 t), synchronised pumps, load cells, locking rings, brackets.
ProductivityA pier in a day.
CostUSD 20,000-200,000 per pier.

Risks and controls

What goes wrong

  • Differential lift cracking the deck, jack slippage, bracket failure.

Quality assurance

Jacking procedure with limits per step, load and displacement logs, survey of the deck during the lift.

Origins

Robert Stephenson lifted the Britannia Bridge tubes with hydraulic presses in 1849–50, building packing under them as they rose; computer-synchronised multi-point jacking with load and displacement feedback has been standard practice since the 1990s.

Examples

Bearing replacements on most ageing viaducts; raising of motorway overpasses for clearance (Spirit of St. Louis Boulevard, Missouri); lifting of new spans onto their supports (Fremont, 1973).

Case studies

Spirit of St. Louis Boulevard Bridge over I-64, MissouriUSA · c. 2014Overpass raised about 0.64 m by hydraulic jacks to cure a substandard 4.45 m clearance; reported at about half the cost of replacement, with a 30-day closure instead of six months.
Fremont Bridge, PortlandUSA · 1973The 275 m, about 5,400 t centre arch section was jacked up about 52 m from barges onto the side spans, a record lift at the time.
Britannia Bridge, Menai StraitUK · 1850Wrought-iron tubes floated into position and raised by hydraulic presses, with masonry and packing built up beneath them as they rose so a press failure could not drop them.

Related methods

Further reading

Enerpac synchronised lifting guides · AASHTO Manual for Bridge Evaluation · AASHTO LRFD Bridge Construction Specifications (jacking and bearing provisions)