Construction methods · Finishing, articulation and maintenance

Bridge demolition and deconstruction

Taking a bridge down is construction in reverse with less information: the old drawings may be wrong and the post-tensioning may be corroded. Decks are cut into pieces and lifted, launched back, lowered by strand jacks, or dropped in a controlled sequence; explosives are used only where a wide exclusion zone can be cleared, which includes some urban sites.

How bridges get built · Finishing, articulation and maintenance · Bridge demolition and deconstruction

Also called: bridge removal, deconstruction, controlled demolition, reverse launching

Bridge demolition and deconstruction — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Investigate: original drawings and records, actual condition (cores, tendon inspection windows, NDT), hazardous materials (asbestos, lead paint, PCBs, contaminated sediment), services on and under the bridge, and what lies below.
  2. Choose the method: saw-cut and lift, reverse erection (cantilever, launching, strand-jack lowering), SPMT removal of whole spans, mechanical breaking from the ground, or explosive felling where an exclusion zone can be held.
  3. Engineer every stage as for erection: stability of the partly removed structure, release of prestress and stored energy, temporary supports, crane and SPMT loads on the remaining structure and ground, and the order of cuts.
  4. Protect what is below with crash decks, catch platforms or sand beds over roads and tracks, debris netting, and turbidity curtains in water; agree possessions and navigation closures.
  5. Strip services, surfacing, parapets and other non-structural items first, then cut and remove the deck in the planned sequence, monitoring movement and crack opening at critical cuts.
  6. Locate and de-tension or encapsulate post-tensioning tendons before cutting, or cut only where they are known to be inactive; treat cantilevers and hinges as able to fail suddenly.
  7. Demolish piers and abutments, cut piles below bed or ground level as permitted, recycle crushed concrete and steel, and restore the site; record what was found for owners of similar bridges.

Key numbers

Where it fits

  • Every replacement project; the game's lateral slide and SPMT sites include removal of the old bridge.

Where it does not

  • Cutting post-tensioned members without knowing the tendon state; dropping spans onto navigation routes or live tracks.

Choosing it

Plant, pace and money

PlantSaws, breakers, cranes, crash decks, barges, hydro-demolition.
ProductivityA span per week for controlled removal.
CostUSD 150-400 per m2 of deck removed, more over rail and water.

Risks and controls

What goes wrong

  • Uncontrolled collapse during cutting (several fatal accidents), falling debris, environmental release.

Quality assurance

Demolition engineering with stage checks, exclusion zones, monitoring during cuts.

Origins

Bridge demolition became an engineering discipline of its own as the motorway bridges of the 1950s–70s reached the end of their lives; accidents during removal, and the finding that post-tensioned decks store energy and hide corrosion, led to codified planning such as BS 6187 and to the rule that removal be designed with the same rigour as erection.

Examples

Old Tappan Zee (2017-2019), Hong Kong flyover removals over live roads, Korean overpass replacements in weekend possessions.

Case studies

Lake Champlain BridgeUSA · 2009The 1929 bridge was closed in October 2009 after inspection found severe deterioration of its piers and was felled with explosives in December 2009; the replacement opened in 2011.
Tappan Zee BridgeUSA · 2017–19Approach and truss spans were removed by floating crane and barge; the last steel truss span was felled into the Hudson with explosives in January 2019 and lifted out.
Polcevera Viaduct (Morandi bridge) remainsItaly · 2019Deck sections were cut and lowered with strand jacks, and the eastern piers were demolished with explosives in June 2019 in a dense urban area.

Related methods

Further reading

NDA Demolition Guidelines · BS 6187 Code of practice for full and partial demolition