Also called: helical pile, screw-in steel pipe pile, rotary penetration pile
How it is done
- Design the helix or toe wing (single or multiple helices, or a wing at the toe of a steel pipe) for the bearing layer and the installation torque, and check the pipe for torsion.
- Set the pile in the rotary head of a crawler rig and start it plumb; advance by rotation with crowd force, keeping the advance per revolution close to the helix pitch so the soil is displaced, not augered out.
- Add sections by welding or bolted couplers and inspect each joint.
- Record torque and depth continuously; stop at the target torque with the minimum embedment in the bearing layer.
- Calibrate the torque-capacity correlation for the site with static or dynamic tests on the first piles.
- Cut off and connect to the cap with a head plate or concrete plug.
Key numbers
- Light helical pilesshafts about 70-300 mm with helices 200-600 mm.
- Rotary-penetration steel pipe piles (Japan)pipes to over 1 m with toe wings about 1.5-2 times the pipe diameter.
- Spoil and vibrationpractically none.
- Productivityabout 5-15 piles per shift.
Where it fits
- Urban sites with noise limits, quick foundations for temporary works and small bridges, retrofit under existing structures with limited headroom.
Where it does not
- Gravels and cobbles that stop the helix; large loads.
Choosing it
- Choose screw piles over driven piles where noise, vibration and spoil are not allowed and loads are light to moderate.
- Choose them for temporary works and falsework that must be removed: they can be unscrewed.
- Prefer bored or driven piles in gravel, cobbles and rock, or where large lateral loads demand large-diameter, thick-walled sections.
Plant, pace and money
PlantRotary rig with torque monitoring.
Productivity5-15 piles per shift.
CostUSD 150-300 per metre for 600-800 mm.
Risks and controls
What goes wrong
- Helix damage, torque-capacity correlation drifting with soil type.
Quality assurance
Torque logs per pile, load tests on a sample.
Origins
Alexander Mitchell patented the screw pile in 1833 and used it for the Maplin Sands lighthouse (1838-41); Victorian piers and colonial bridges followed. Large rotary-penetration steel pipe piles with toe wings were developed in Japan in the late 20th century as low-noise, spoil-free bearing piles.
Examples
Japanese highway viaducts near housing; falsework foundations.
Case studies
Maplin Sands Lighthouse, Thames estuaryUK · 1838-1841Mitchell's first major use of screw piles: a lighthouse on iron screw piles in soft estuary sand.
West Pier, BrightonUK · 1866Eugenius Birch's pier stood on cast-iron columns screwed into the seabed, the method used for many Victorian seaside piers.
Related methods
Further reading
JIS A 5525 · ICC-ES AC358 · Perko, Helical Piles: A Practical Guide to Design and Installation