Also called: rock armour, gabion mattress, articulated concrete blocks, scour countermeasures
How it is done
- Size the stone from the design velocity near the pier with pier shape factors (HEC-23), and check it against waves and ship propeller wash where they apply.
- Design the filter (geotextile or graded granular) and the layer: at least three times D50 thick, extending at least two pier widths from the pier face all round.
- Excavate or dredge a pocket so that the top of the armour sits at or below the existing bed; raised aprons cause scour at their own edges.
- Place the filter: weighted geotextile panels or sand-filled geocontainers under water, or a granular filter by bottom-dump or skip.
- Place the riprap by excavator, crane skip or side-dumping vessel, working outward from the pier in controlled layers; confirm thickness by multibeam survey.
- Where stone of the size needed is not available, use articulated concrete blocks, grout-filled mattresses, gabion mattresses or partially grouted riprap instead.
- Inspect after placement and after every significant flood, replace displaced stone, and keep a monitoring plan with closure triggers for scour-critical bridges.
Key numbers
- Pier riprap (HEC-23)D50 = 0.692 (K·V)² / [(Ss − 1)·2g], with K = 1.5 for round-nosed and 1.7 for rectangular piers.
- Layer thickness at least 3 D50; extent at least two pier widths from the pier face.
- Typical D50 for river piersabout 0.3–1.0 m; rock density at least about 2,600 kg/m³.
- Granular filter ruleD15 of the filter no more than about 4–5 times D85 of the base soil.
- Costabout USD 60–150 per tonne placed.
Where it fits
- Existing bridges with scour vulnerability, river piers where deep foundations are already fixed, bank protection at abutments.
Where it does not
- Relying on riprap alone for new piers: design the foundation for scour and treat the armour as a second line.
Choosing it
- For new bridges design the foundations for full scour and use armour as a second line; for existing bridges on shallow foundations, armour is often the economic fix.
- Choose riprap where suitable stone is available and access allows; prefer articulated concrete blocks or grout-filled mattresses where the stone size needed is not available.
- Prefer flexible armour (riprap, block mats) to rigid aprons, which crack and are undermined at their edges.
- For scour-critical bridges awaiting replacement, combine armour with monitoring and a closure plan rather than relying on armour alone.
Plant, pace and money
PlantExcavator or barge crane, dump trucks or hopper barges, divers for inspection.
Productivity500-2,000 t of stone per day depending on access.
CostUSD 60-150 per tonne placed.
Risks and controls
What goes wrong
- Undersized stone washing out; edge failure where the armour meets the bed; winnowing of fines through a missing filter.
Quality assurance
Stone grading certificates, post-placement bathymetry, inspection after the first flood.
Origins
Rock armour is as old as river engineering; systematic US countermeasure guidance, FHWA HEC-23, was first published in 1997 after the scour programme set off by Schoharie Creek, and the CIRIA/CUR/CETMEF Rock Manual (2007) is the European reference.
Examples
FHWA HEC-23 sets out the countermeasure options and design guidelines used in the US; rock aprons and mattresses are the standard retrofit for older river bridges on spread footings or short piles in Europe and Asia.
Case studies
Schoharie Creek BridgeUSA · 1987Riprap around the spread footings had not been maintained; a flood scoured beneath a pier and two spans fell, killing 10 people.
Malahide ViaductIreland · 2009A pier collapsed just after a train had crossed; investigators found that scour had removed the rock armour and weir protecting the foundations, which had not been inspected or maintained under water.
Inn River motorway bridge near InnsbruckAustria · 1990After a scoured pier sank about 1.2 m and tilted the decks, about 38,000 t of boulders were dumped around its base, grout was injected under the foundation, and cables tied the pier to the bank.
Related methods
Further reading
FHWA HEC-23 · CIRIA C683 Rock Manual · Lagasse et al., Bridge Scour and Stream Instability Countermeasures (FHWA HEC-23, 3rd edition) · Melville and Coleman, Bridge Scour