Also called: raft foundation, combined footing
How it is done
- Confirm by settlement analysis that the raft keeps differential settlement between columns within tolerance; check punching shear at each column and fix the pour sequence and joint positions.
- Excavate the full footprint with support and groundwater control; inspect the formation as for spread footings and blind it the same day.
- Where groundwater is high, lay a waterproofing membrane or specify watertight concrete, and check flotation for the construction stage when the raft is still light and the water table recovers.
- Fix two-way top and bottom mats with shear links at the column zones; mats 1-3 m thick need steel chairs or trestles strong enough to carry the top layer, workers and pump lines.
- Prepare the thermal control plan: low-heat binder (slag or fly ash), a placing-temperature limit, insulation, and cooling pipes and thermocouples for pours thicker than about 1.5-2 m.
- Pour in one continuous operation, or in planned bays or layers with keyed and roughened construction joints; arrange two batching sources and a standby pump for large rafts.
- Cure under insulation until the core-to-surface temperature difference has fallen within the limit, then backfill and set settlement points at the column positions.
Key numbers
- Thicknesstypically 1-3 m under multi-column bents and pylon bases; anchorage blocks are far thicker.
- Net bearing pressure on soilcommonly 100-300 kPa; a raft becomes economic when pads would cover more than about half the plan.
- Pour size500-5,000 m3 placed continuously is common, at 50-150 m3/h per pump.
- Thermal limitspeak core temperature 70 C; core-to-surface difference about 20 C.
- Construction-stage flotationfactor of safety of at least about 1.1 against uplift before the superstructure weight arrives.
Where it fits
- Medium-strength ground under closely spaced columns, pylon bases on dense sand or weak rock, sites where differential settlement between columns must be avoided.
Where it does not
- Highly variable ground across the footprint: the raft will tilt rather than settle evenly.
Choosing it
- Choose a raft over separate pads when column loads are close together, pads would overlap or cover more than about half the plan, or differential settlement between columns must be limited.
- Prefer a piled raft or a pile group when the ground under the raft is compressible enough that settlement, not bearing, governs.
- Prefer separate pads on uniform ground with widely spaced columns: less concrete and less thermal risk.
- For suspension bridge anchorages, a gravity block on a raft is chosen over a tunnel anchorage when the rock is not strong or massive enough to carry the cable pull in shear.
Plant, pace and money
PlantAs for spread footings plus a larger concrete supply and thermal control.
ProductivityA 1,000 m3 raft is a two- to three-week operation including curing.
CostSimilar unit rate to pads; total cost dominated by concrete volume.
Risks and controls
What goes wrong
- Thermal cracking in mass concrete; uplift under high groundwater.
Quality assurance
Thermal monitoring of the pour, cube tests, membrane integrity.
Origins
Combined footings and rafts became routine with reinforced concrete in the early 20th century; in bridge work their largest applications are the gravity anchorages of suspension bridges and the bases of pylons and multi-column bents.
Examples
Gravity anchorages of suspension bridges on rock or dense ground; pylon bases and multi-column bents where pads would merge.
Case studies
Akashi Kaikyo Bridge (Awaji-side anchorage 4A)Japan · 1998The Awaji anchorage is a gravity block on a spread (direct) foundation, while the Kobe-side anchorage needed an 85 m diameter diaphragm-wall shaft: the two ends show where a direct raft is and is not possible.
Yangluo Yangtze River Bridge (north anchorage)China · 2007Gravity anchorage of a 1,280 m suspension span set on an enlarged spread foundation in a deep, battered open excavation; the south anchorage on poorer ground needed a 73 m diameter diaphragm-wall shaft.
Related methods
Further reading
ACI 336 · Eurocode 7-1 · ACI 336.2R Suggested analysis and design procedures for combined footings and mats · Poulos, Piled raft foundations: design and applications (Geotechnique, 2001)