Construction methods · Shallow foundations, cofferdams and dewatering

Mat (raft) foundation

One large slab under a group of columns or a wide pier, spreading the load over ground that would fail under individual pads. Used under multi-column bents, portal frames and pylon bases where the loads are close together.

Also called: raft foundation, combined footing

How it is done

  1. Confirm by settlement analysis that the raft keeps differential settlement between columns within tolerance; check punching shear at each column and fix the pour sequence and joint positions.
  2. Excavate the full footprint with support and groundwater control; inspect the formation as for spread footings and blind it the same day.
  3. Where groundwater is high, lay a waterproofing membrane or specify watertight concrete, and check flotation for the construction stage when the raft is still light and the water table recovers.
  4. Fix two-way top and bottom mats with shear links at the column zones; mats 1-3 m thick need steel chairs or trestles strong enough to carry the top layer, workers and pump lines.
  5. Prepare the thermal control plan: low-heat binder (slag or fly ash), a placing-temperature limit, insulation, and cooling pipes and thermocouples for pours thicker than about 1.5-2 m.
  6. Pour in one continuous operation, or in planned bays or layers with keyed and roughened construction joints; arrange two batching sources and a standby pump for large rafts.
  7. Cure under insulation until the core-to-surface temperature difference has fallen within the limit, then backfill and set settlement points at the column positions.

Key numbers

Where it fits

  • Medium-strength ground under closely spaced columns, pylon bases on dense sand or weak rock, sites where differential settlement between columns must be avoided.

Where it does not

  • Highly variable ground across the footprint: the raft will tilt rather than settle evenly.

Choosing it

Plant, pace and money

PlantAs for spread footings plus a larger concrete supply and thermal control.
ProductivityA 1,000 m3 raft is a two- to three-week operation including curing.
CostSimilar unit rate to pads; total cost dominated by concrete volume.

Risks and controls

What goes wrong

  • Thermal cracking in mass concrete; uplift under high groundwater.

Quality assurance

Thermal monitoring of the pour, cube tests, membrane integrity.

Origins

Combined footings and rafts became routine with reinforced concrete in the early 20th century; in bridge work their largest applications are the gravity anchorages of suspension bridges and the bases of pylons and multi-column bents.

Examples

Gravity anchorages of suspension bridges on rock or dense ground; pylon bases and multi-column bents where pads would merge.

Case studies

Akashi Kaikyo Bridge (Awaji-side anchorage 4A)Japan · 1998The Awaji anchorage is a gravity block on a spread (direct) foundation, while the Kobe-side anchorage needed an 85 m diameter diaphragm-wall shaft: the two ends show where a direct raft is and is not possible.
Yangluo Yangtze River Bridge (north anchorage)China · 2007Gravity anchorage of a 1,280 m suspension span set on an enlarged spread foundation in a deep, battered open excavation; the south anchorage on poorer ground needed a 73 m diameter diaphragm-wall shaft.

Related methods

Further reading

ACI 336 · Eurocode 7-1 · ACI 336.2R Suggested analysis and design procedures for combined footings and mats · Poulos, Piled raft foundations: design and applications (Geotechnique, 2001)