Construction methods · Cast-in-place concrete decks

Falsework on temporary piles (shallow water)

Cast-in-place on falsework carried by temporary steel piles driven into the riverbed, so the method survives 1-3 m of slow water outside the flood season. The classic construction of small river and canal bridges before precast girders took over.

How bridges get built · Cast-in-place concrete decks · Falsework on temporary piles (shallow water)

Also called: piled falsework, trestle falsework, falsework in water

Falsework on temporary piles (shallow water) — concept diagram
Concept diagram (TheBridgeEng)

How it is done

  1. Collect the hydrology for the construction window (water levels, velocities, flood season, debris, ice, navigation) and design the falsework for current, debris and boat impact as well as the pour.
  2. Drive temporary steel pipe or H-piles in bents from a barge, or pitch and drive from the previous bent, usually with a vibratory hammer; record penetrations and check capacity.
  3. Brace each bent at low water, cap it with head beams and span between bents with steel beams or trusses; build the soffit as for ground falsework, including pile shortening and beam deflection in the casting levels.
  4. Protect the bents against scour and debris with rock, deflectors or booms, and monitor bed levels around the piles.
  5. Pour the deck in the planned sequence with settlement monitoring, and keep a flood watch with trigger levels for stopping work and evacuating.
  6. After stressing and striking, remove the beams and extract the piles with the vibratory hammer before the flood season, or cut them below bed level where allowed.

Key numbers

Where it fits

  • Slow rivers and canals up to about 3 m deep, spans 20-45 m, dry-season programmes.

Where it does not

  • Water beyond 3-5 m, velocities over 2 m/s, navigable routes, flood seasons.

Choosing it

Plant, pace and money

PlantPiling rig or barge with vibro-hammer, temporary piles, falsework, formwork.
ProductivitySlower than ground falsework: allow 45-60 days per span.
CostAdds USD 100-250 per m2 for the piles and bracing.

Risks and controls

What goes wrong

  • Flood taking the falsework, debris loading, scour of the temporary piles, boat impact.

Quality assurance

Flood watch and evacuation plan, pile driving records, bracing inspection.

Origins

Piled staging in rivers is as old as timber centering; steel H and pipe piles installed and recovered with vibratory hammers made it routine and reusable from the 1960s.

Examples

Small river bridges in Korea, Japan and Europe until the 1980s; still used for canals and irrigation crossings.

In the bridge game

What Bridge Master applies when you pick it

Deck types: RC slab, Voided slab, RC T-beam, RC box, PSC box (cast in place), Rigid frame, Concrete arch, PSC box, balanced cantilever, Extradosed, Network tied arch. Spans 20-45 m, up to 60 m.

  • +25: Shallow, slow water: piled falsework is the cheap answer.
  • -40: Too deep for piled falsework.
  • -30: Fast water loads the temporary piles and debris piles up.
  • -15: Only in the dry season; the falsework must be out before the floods.
  • -30: Blocks the navigation route.
  • not allowed: Piled falsework in 5 m+ of water is not a temporary works design, it is a bridge.
  • not allowed: Temporary piles in the water where in-water works are banned.
  • not allowed: Piled falsework is for spans over shallow water; on dry ground use ground falsework.

Try it in the game →

Related methods

Further reading

BS 5975 · Japan Road Association temporary works