Also called: match casting, short-line casting, long-line casting, casting yard
How it is done
- Plan the yard from the erection rate: number of cells or beds, cage jig area, curing, storage on three-point supports and haul routes, keeping production ahead of erection.
- Short-line: cast each segment in a fixed mould between a fixed bulkhead and the previous segment, which is moved on an adjustable cart to the corrected position for the next segment's geometry.
- Long-line: cast the segments in sequence on a continuous soffit bed built to the cantilever profile including camber, with the side forms moving along the bed.
- Place the prefabricated cage with ducts, shear keys, blisters and inserts; pour, cure (often with heat) and strip the next morning.
- Survey both segments before and after each pour on six control points per segment (four level bolts and two centreline points) and feed the as-cast errors into the next set-up.
- Separate the match-cast pair with its bond breaker, move the old segment to storage, and inspect, repair and record it.
- Deliver in erection order with the casting records, so erection survey can be compared with the casting curve.
Key numbers
- Productionone segment per short-line cell per day
- Geometry controlsix survey points per segment
- Yard size6–12 short-line cells for a large viaduct
- Segment length 2.5–4 m; weight typically 30–150 t
- Costyard USD 5–20 million; segments USD 600–900 per m3
Where it fits
- All precast segmental decks; short-line for curves and variable geometry, long-line for straight repetitive cantilevers.
Where it does not
- Yards without a geometry control engineer; storage stacking that cracks segments.
Choosing it
- Choose short-line casting for curved and variable geometry and a compact yard; it depends on rigorous geometry control at every segment.
- Choose long-line casting for straight, repetitive cantilevers where a long bed fits the site; geometry is simpler but the yard is large.
- Size the number of cells from the erection rate: an idle gantry costs more than an extra cell.
Plant, pace and money
PlantCasting cells or bed, rebar jigs, concrete plant, steam curing, gantry cranes, survey.
ProductivityOne segment per cell per day; 6-12 cells for a large viaduct.
CostYard USD 5-20 million; segments USD 600-900 per m3.
Risks and controls
What goes wrong
- Geometry error accumulating and appearing at closure, match-cast face damage, shear key breakage.
Quality assurance
Casting curve reports per segment, mould checks, concrete strength at stripping.
Origins
Match casting was introduced by Jean Muller and Campenon Bernard on the Choisy-le-Roi bridge in the early 1960s; short-line casting with computed geometry correction became the norm for curved viaducts as computing made the corrections routine.
Examples
Every segmental project in the game's precast methods.
Case studies
Choisy-le-Roi Bridge, SeineFrance · early 1960sThe first match-cast segments, the technique every precast segmental yard still uses.
Linn Cove Viaduct, North CarolinaUSA · 1983153 segments with no two alike and only one straight, cast with geometry controlled to 0.001 ft (0.3 mm); no segment was rejected.