Construction methods · Precast concrete decks

Segment casting: short-line and long-line match casting

Precast segmental bridges are only as good as the yard. Match casting pours each segment against the previous one so the joints fit perfectly; short-line does it in a fixed cell with the previous segment moved into position, long-line casts a whole cantilever on a long bed. Geometry control in the yard decides the geometry of the bridge.

How bridges get built · Precast concrete decks · Segment casting: short-line and long-line match casting

Also called: match casting, short-line casting, long-line casting, casting yard

How it is done

  1. Plan the yard from the erection rate: number of cells or beds, cage jig area, curing, storage on three-point supports and haul routes, keeping production ahead of erection.
  2. Short-line: cast each segment in a fixed mould between a fixed bulkhead and the previous segment, which is moved on an adjustable cart to the corrected position for the next segment's geometry.
  3. Long-line: cast the segments in sequence on a continuous soffit bed built to the cantilever profile including camber, with the side forms moving along the bed.
  4. Place the prefabricated cage with ducts, shear keys, blisters and inserts; pour, cure (often with heat) and strip the next morning.
  5. Survey both segments before and after each pour on six control points per segment (four level bolts and two centreline points) and feed the as-cast errors into the next set-up.
  6. Separate the match-cast pair with its bond breaker, move the old segment to storage, and inspect, repair and record it.
  7. Deliver in erection order with the casting records, so erection survey can be compared with the casting curve.

Key numbers

Where it fits

  • All precast segmental decks; short-line for curves and variable geometry, long-line for straight repetitive cantilevers.

Where it does not

  • Yards without a geometry control engineer; storage stacking that cracks segments.

Choosing it

Plant, pace and money

PlantCasting cells or bed, rebar jigs, concrete plant, steam curing, gantry cranes, survey.
ProductivityOne segment per cell per day; 6-12 cells for a large viaduct.
CostYard USD 5-20 million; segments USD 600-900 per m3.

Risks and controls

What goes wrong

  • Geometry error accumulating and appearing at closure, match-cast face damage, shear key breakage.

Quality assurance

Casting curve reports per segment, mould checks, concrete strength at stripping.

Origins

Match casting was introduced by Jean Muller and Campenon Bernard on the Choisy-le-Roi bridge in the early 1960s; short-line casting with computed geometry correction became the norm for curved viaducts as computing made the corrections routine.

Examples

Every segmental project in the game's precast methods.

Case studies

Choisy-le-Roi Bridge, SeineFrance · early 1960sThe first match-cast segments, the technique every precast segmental yard still uses.
Linn Cove Viaduct, North CarolinaUSA · 1983153 segments with no two alike and only one straight, cast with geometry controlled to 0.001 ft (0.3 mm); no segment was rejected.

Related methods

Further reading

ASBI Construction Practices Handbook · AASHTO Guide Specifications for Segmental Bridges